Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Triple-Chamber Calcium-Zinc PVC Window Profile
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
29 s
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
8.80 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
111 s
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.02%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Twin-Screw Conical Extrude
1,995 < 2,800/day
Limit: downtime
Twin-Screw Conical Extrude: capacity 1,995/day vs demand 2,800/day. Main limit: downtime. Raw C/T 31 s, effective C/T 39 s.
Quality (RTY)
91.5%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€167,552
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
238.8 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Regional PVC Resin Pr…
Rigid uPVC Dryblend
1x / week · LT 5d
PRODUCTION CONTROL / ERP
Extrusion ERP
Large Campaign Mold Schedule
CUSTOMER
Fenestration Window M…
2,800 parts/d
Takt: 29 s
EDI / Daily Truck
MRP / 1x / week
★ PACEMAKER
IN
Insert a step at the start
+
I
4,480
1.60 d
Drag to reorder step 1
PREP ZONE
1. Automated Silo D…
×1
Continuous Flow
C/T
19 s
C/O
20 min
Availability
96%
Quality FPY
99.4%
Batch / EPEI
4200 / 2d
OEE
94.5%
i
Insert a step here
+
I
6,160
2.20 d
SMED
SMED Quic…
Drag to reorder step 2
MOLDING HALL
2. Twin-Screw Conic…
×2
BOTTLENECK
C/T
31 s
C/O
95 min
Availability
82%
Quality FPY
96.5%
Batch / EPEI
5600 / 4d
OEE
76.3%
i
Insert a step here
+
I
3,920
1.40 d
Drag to reorder step 3
QUALITY BAY
3. Vacuum Calibrati…
×2
Push Flow
C/T
21 s
C/O
15 min
Availability
93%
Quality FPY
97.5%
Batch / EPEI
1400 / 1d
OEE
88.7%
i
Insert a step here
+
I
3,360
1.20 d
Drag to reorder step 4
ASSEMBLY
4. Co-Extruded TPE …
×3
Push Flow
C/T
24 s
C/O
20 min
Availability
91%
Quality FPY
98.2%
Batch / EPEI
1400 / 1d
OEE
86.7%
i
Insert a step here
+
I
2,520
0.90 d
Drag to reorder step 5
DISPATCH
5. Foil Lamination …
×1
FIFO Lane
C/T
17 s
C/O
10 min
Availability
97%
Quality FPY
99.6%
Batch / EPEI
1120 / 1d
OEE
94.8%
i
Insert a step at the end
+
I
4,200
1.50 d
Finished Goods
OUT
1.60 d
VA 19 s
2.20 d
VA 31 s
1.40 d
VA 21 s
1.20 d
VA 24 s
0.90 d
VA 17 s
1.50 d
Total Lead Time
8.80 d
VA Time
111 s
PCE
0.02%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step