Neutral-Cure Oxime Silicone Sealant Cartridge
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
1.7 s
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
8.50 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
6.9 s
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.00%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Lab Skin-Over & Shore A QC
23,940 < 32,000/day
Limit: downtime
Lab Skin-Over & Shore A QC: capacity 23,940/day vs demand 32,000/day. Main limit: downtime. Raw C/T 1.8 s, effective C/T 2.2 s.
Quality (RTY)
91.3%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€448,800
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
4,671.7 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
OH-Polymer & Silica S…
Silicone Base & Fumed S…
2x / week · LT 5d
PRODUCTION CONTROL / ERP
Chemical ERP
Kettle Recipe Campaign
CUSTOMER
Construction & Hardwa…
32,000 units/d
Takt: 1.7 s
EDI / Daily ADR / Van
MRP / 2x / week
★ PACEMAKER
IN
Insert a step at the start
+
I
44,800
1.40 d
Drag to reorder step 1
TANK FARM
1. Planetary Vacuum…
×1
Continuous Flow
C/T
1.2 s
C/O
20 min
Availability
95%
Quality FPY
99.1%
Batch / EPEI
48000 / 2d
OEE
92.8%
i
Insert a step here
+
I
51,200
1.60 d
Drag to reorder step 2
BLEND BAY
2. Static Mixer Cat…
×2
Push Flow
C/T
1.4 s
C/O
45 min
Availability
91%
Quality FPY
98.2%
Batch / EPEI
38400 / 2d
OEE
85.6%
i
Insert a step here
+
I
64,000
2.00 d
AUTOMATION
In-Line B…
Drag to reorder step 3
CHEM QC LAB
3. Lab Skin-Over & …
×2
BOTTLENECK
C/T
1.8 s
C/O
18 min
Availability
85%
Quality FPY
95.8%
Batch / EPEI
32000 / 1d
OEE
79.8%
i
Insert a step here
+
I
35,200
1.10 d
Drag to reorder step 4
PACK LINE
4. Automated Tube F…
×2
FIFO Lane
C/T
1.3 s
C/O
30 min
Availability
92%
Quality FPY
98.4%
Batch / EPEI
19200 / 1d
OEE
85.5%
i
FIFO
Insert a step here
+
I
28,800
0.90 d
Drag to reorder step 5
ADR DOCK
5. 12-Pack Display …
×2
Continuous Flow
C/T
1.2 s
C/O
10 min
Availability
97%
Quality FPY
99.5%
Batch / EPEI
12800 / 1d
OEE
93.8%
i
Insert a step at the end
+
I
48,000
1.50 d
Finished Goods
OUT
1.40 d
VA 1.2 s
1.60 d
VA 1.4 s
2.00 d
VA 1.8 s
1.10 d
VA 1.3 s
0.90 d
VA 1.2 s
1.50 d
Total Lead Time
8.50 d
VA Time
6.9 s
PCE
0.00%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen