Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Hydromill Concrete Diaphragm Station Wall
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
1.9 h
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
8.99 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
7.4 h
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
5.48%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Ultrasonic Verticality Check
5 < 8/day
Limit: downtime
Ultrasonic Verticality Check: capacity 5/day vs demand 8/day. Main limit: downtime. Raw C/T 2.0 h, effective C/T 2.5 h.
Quality (RTY)
86.7%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€986,000
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
42.1 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Bentonite Plant & Reb…
Tremie Concrete & Steel…
Daily Batch Mix · LT 2d
PRODUCTION CONTROL / ERP
GeotechERP
Weather & Concrete Pour Hold
CUSTOMER
Deep Metro Stations
8 cases/d
Takt: 1.9 h
EDI / Milestone Handover
MRP / Daily Batch Mix
★ PACEMAKER
IN
Insert a step at the start
+
I
12
1.50 d
Drag to reorder step 1
CIVIL PREP
1. Concrete Guide-W…
×4
Push Flow
C/T
1.3 h
C/O
25 min
Availability
94%
Quality FPY
97.6%
Batch / EPEI
6 / 1d
OEE
88.3%
i
Insert a step here
+
I
14
1.75 d
Drag to reorder step 2
STRUCTURAL
2. Slurry Wall Pane…
×5
Push Flow
C/T
1.6 h
C/O
30 min
Availability
91%
Quality FPY
96.5%
Batch / EPEI
5 / 1d
OEE
83.1%
i
Insert a step here
+
I
18
2.25 d
AUTOMATION
Self-Comp…
Drag to reorder step 3
CRITICAL PATH
3. Ultrasonic Verti…
×6
BOTTLENECK
C/T
2.0 h
C/O
40 min
Availability
84%
Quality FPY
94.8%
Batch / EPEI
4 / 1d
OEE
72.6%
i
Insert a step here
+
I
13
1.63 d
Drag to reorder step 4
CURING
4. Crawler Crane St…
×3
FIFO Lane
C/T
1.5 h
C/O
20 min
Availability
93%
Quality FPY
98.0%
Batch / EPEI
4 / 1d
OEE
87.1%
i
FIFO
Insert a step here
+
I
6
0.75 d
Drag to reorder step 5
AS-BUILT QC
5. Double-Tremie Co…
×2
FIFO Lane
C/T
1.1 h
C/O
10 min
Availability
97%
Quality FPY
99.1%
Batch / EPEI
2 / 1d
OEE
91.9%
i
Insert a step at the end
+
I
5
0.63 d
Finished Goods
OUT
1.50 d
VA 1.3 h
1.75 d
VA 1.6 h
2.25 d
VA 2.0 h
1.63 d
VA 1.5 h
0.75 d
VA 1.1 h
0.63 d
Total Lead Time
8.99 d
VA Time
7.4 h
PCE
5.48%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step