1600mm Ductile Iron Potable Water Mainline Lay
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
6.9 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
8.57 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
27.3 min
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.71%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Thrust Block & Valve Chamber
40 < 65/day
Limit: changeovers
Thrust Block & Valve Chamber: capacity 40/day vs demand 65/day. Main limit: changeovers. Raw C/T 7.5 min, effective C/T 9.4 min.
Quality (RTY)
86.7%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€801,850
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
341.8 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Ductile Iron Pipe Pro…
Cement-Lined Ductile Pi…
Daily Batch Mix · LT 2d
PRODUCTION CONTROL / ERP
PipeBuild ERP
Weather & Concrete Pour Hold
CUSTOMER
Regional Water Author…
65 parts/d
Takt: 6.9 min
EDI / Milestone Handover
MRP / Daily Batch Mix
★ PACEMAKER
IN
Insert a step at the start
+
I
98
1.51 d
Drag to reorder step 1
CIVIL PREP
1. Laser-Graded Tre…
×4
Push Flow
C/T
4.7 min
C/O
25 min
Availability
94%
Quality FPY
97.6%
Batch / EPEI
52 / 1d
OEE
85.4%
i
Insert a step here
+
I
117
1.80 d
Drag to reorder step 2
STRUCTURAL
2. Crane Lower & Pu…
×5
Push Flow
C/T
5.8 min
C/O
30 min
Availability
91%
Quality FPY
96.5%
Batch / EPEI
39 / 1d
OEE
78.1%
i
Insert a step here
+
I
143
2.20 d
AUTOMATION
Self-Comp…
Drag to reorder step 3
CRITICAL PATH
3. Thrust Block & V…
×6
BOTTLENECK
C/T
7.5 min
C/O
40 min
Availability
84%
Quality FPY
94.8%
Batch / EPEI
33 / 1d
OEE
65.7%
i
Insert a step here
+
I
104
1.60 d
Drag to reorder step 4
CURING
4. 30-Bar Hydro & C…
×3
FIFO Lane
C/T
5.4 min
C/O
20 min
Availability
93%
Quality FPY
98.0%
Batch / EPEI
33 / 1d
OEE
83.2%
i
FIFO
Insert a step here
+
I
52
0.80 d
Drag to reorder step 5
AS-BUILT QC
5. Compacted Sand &…
×2
FIFO Lane
C/T
3.9 min
C/O
10 min
Availability
97%
Quality FPY
99.1%
Batch / EPEI
20 / 1d
OEE
89.2%
i
Insert a step at the end
+
I
39
0.60 d
Finished Goods
OUT
1.51 d
VA 4.7 min
1.80 d
VA 5.8 min
2.20 d
VA 7.5 min
1.60 d
VA 5.4 min
0.80 d
VA 3.9 min
0.60 d
Total Lead Time
8.57 d
VA Time
27.3 min
PCE
0.71%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step