Grade-A Office Tower Floor MEP First-Fix Takt
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
32.1 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
6.34 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
2.0 h
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
4.20%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Busbar, Tray & Fire Sprinkler
9 < 14/day
Limit: changeovers
Busbar, Tray & Fire Sprinkler: capacity 9/day vs demand 14/day. Main limit: changeovers. Raw C/T 34.4 min, effective C/T 43.1 min.
Quality (RTY)
86.7%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€238,000
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
6.4 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
MEP Electrical & Duct…
Cable Trays, VAVs & Ris…
2x / week · LT 4d
PRODUCTION CONTROL / ERP
Takt Planning / BIM
Trade Stacking Clash Delays
CUSTOMER
Commercial Tower Deve…
14 rooms/d
Takt: 32.1 min
EDI / Floor Turnkey
MRP / 2x / week
★ PACEMAKER
IN
Insert a step at the start
+
I
14
1.00 d
Drag to reorder step 1
STAGING ZONE
1. Laser Slab Penet…
×2
FIFO Lane
C/T
19.9 min
C/O
10 min
Availability
96%
Quality FPY
98.4%
Batch / EPEI
6 / 1d
OEE
89.6%
i
FIFO
Insert a step here
+
I
18
1.29 d
Drag to reorder step 2
FIRST FIX
2. Primary Duct & C…
×4
Push Flow
C/T
25.1 min
C/O
12 min
Availability
93%
Quality FPY
97.6%
Batch / EPEI
4 / 1d
OEE
82.3%
i
Insert a step here
+
I
25
1.79 d
BALANCING
Pull Takt…
Drag to reorder step 3
ZONE TAKT
3. Busbar, Tray & F…
×5
BOTTLENECK
C/T
34.4 min
C/O
20 min
Availability
85%
Quality FPY
93.8%
Batch / EPEI
4 / 1d
OEE
67.3%
i
Insert a step here
+
I
13
0.93 d
Drag to reorder step 4
TRADE TEST
4. Pressure & Conti…
×2
FIFO Lane
C/T
23.8 min
C/O
8 min
Availability
95%
Quality FPY
97.4%
Batch / EPEI
3 / 1d
OEE
84.9%
i
FIFO
Insert a step here
+
I
7
0.50 d
Drag to reorder step 5
HANDOVER
5. Ceiling Close Si…
×2
Continuous Flow
C/T
16.7 min
C/O
5 min
Availability
97%
Quality FPY
98.8%
Batch / EPEI
2 / 1d
OEE
88.4%
i
Insert a step at the end
+
I
8
0.57 d
Finished Goods
OUT
1.00 d
VA 19.9 min
1.29 d
VA 25.1 min
1.79 d
VA 34.4 min
0.93 d
VA 23.8 min
0.50 d
VA 16.7 min
0.57 d
Total Lead Time
6.34 d
VA Time
2.0 h
PCE
4.20%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step