Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
500kW Commercial Flat-Roof Ballasted Solar Fit
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
25.0 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
6.26 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
1.6 h
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
3.31%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Module Clamp & DC Micro-Wire
11 < 18/day
Limit: changeovers
Module Clamp & DC Micro-Wire: capacity 11/day vs demand 18/day. Main limit: changeovers. Raw C/T 26.8 min, effective C/T 33.6 min.
Quality (RTY)
86.7%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€348,800
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
8.3 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Tier-1 Bifacial PV & …
Al East-West Ballast Mo…
2x / week · LT 4d
PRODUCTION CONTROL / ERP
SolarRoof ERP
Trade Stacking Clash Delays
CUSTOMER
Warehouse REIT Roofs
18 skids/d
Takt: 25.0 min
EDI / Floor Turnkey
MRP / 2x / week
★ PACEMAKER
IN
Insert a step at the start
+
I
18
1.00 d
Drag to reorder step 1
STAGING ZONE
1. Roof Crane Mater…
×2
FIFO Lane
C/T
15.5 min
C/O
10 min
Availability
96%
Quality FPY
98.4%
Batch / EPEI
7 / 1d
OEE
89.1%
i
FIFO
Insert a step here
+
I
23
1.28 d
Drag to reorder step 2
FIRST FIX
2. Protective EPDM …
×4
Push Flow
C/T
19.5 min
C/O
12 min
Availability
93%
Quality FPY
97.6%
Batch / EPEI
5 / 1d
OEE
82.1%
i
Insert a step here
+
I
32
1.78 d
BALANCING
Pull Takt…
Drag to reorder step 3
ZONE TAKT
3. Module Clamp & D…
×5
BOTTLENECK
C/T
26.8 min
C/O
20 min
Availability
85%
Quality FPY
93.8%
Batch / EPEI
5 / 1d
OEE
67.0%
i
Insert a step here
+
I
16
0.89 d
Drag to reorder step 4
TRADE TEST
4. Combiner, Invert…
×2
FIFO Lane
C/T
18.5 min
C/O
8 min
Availability
95%
Quality FPY
97.4%
Batch / EPEI
4 / 1d
OEE
85.1%
i
FIFO
Insert a step here
+
I
9
0.50 d
Drag to reorder step 5
HANDOVER
5. IV Curve, Therma…
×2
Continuous Flow
C/T
13.0 min
C/O
5 min
Availability
97%
Quality FPY
98.8%
Batch / EPEI
3 / 1d
OEE
89.4%
i
Insert a step at the end
+
I
11
0.61 d
Finished Goods
OUT
1.00 d
VA 15.5 min
1.28 d
VA 19.5 min
1.78 d
VA 26.8 min
0.89 d
VA 18.5 min
0.50 d
VA 13.0 min
0.61 d
Total Lead Time
6.26 d
VA Time
1.6 h
PCE
3.31%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen