Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Unitized Curtain-Wall Aluminum-Glass Facade
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
13.8 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
7.06 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
52.4 min
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.82%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
IGU Structural Silicone Glaze
45 < 65/day
Limit: downtime
IGU Structural Silicone Glaze: capacity 45/day vs demand 65/day. Main limit: downtime. Raw C/T 14.8 min, effective C/T 18.5 min.
Quality (RTY)
85.9%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€750,750
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
188.8 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Aluminium Facade Prof…
Thermally Broken Al & I…
Weekly Steel/MEP · LT 8d
PRODUCTION CONTROL / ERP
FacadeBIM ERP
Project Job-Shop Push
CUSTOMER
High-Rise Skyscrapers
65 modules/d
Takt: 13.8 min
EDI / Daily Crane Slot
MRP / Weekly Steel/MEP
★ PACEMAKER
IN
Insert a step at the start
+
I
91
1.40 d
Drag to reorder step 1
BAY 1 FRAME
1. 4-Axis Al Frame …
×4
Push Flow
C/T
9.0 min
C/O
35 min
Availability
93%
Quality FPY
98.2%
Batch / EPEI
52 / 2d
OEE
86.9%
i
Insert a step here
+
I
78
1.20 d
Drag to reorder step 2
BAY 2 SHELL
2. EPDM Gasket & Co…
×4
Push Flow
C/T
10.0 min
C/O
20 min
Availability
94%
Quality FPY
97.6%
Batch / EPEI
33 / 1d
OEE
87.7%
i
Insert a step here
+
I
130
2.00 d
BALANCING
Pre-Built…
Drag to reorder step 3
BAY 3 MEP
3. IGU Structural S…
×5
BOTTLENECK
C/T
14.8 min
C/O
30 min
Availability
86%
Quality FPY
93.0%
Batch / EPEI
26 / 1d
OEE
73.3%
i
Insert a step here
+
I
65
1.00 d
Drag to reorder step 4
BAY 4 FINISH
4. Weather Cure & W…
×4
FIFO Lane
C/T
11.1 min
C/O
15 min
Availability
94%
Quality FPY
97.2%
Batch / EPEI
20 / 1d
OEE
86.4%
i
FIFO
Insert a step here
+
I
39
0.60 d
Drag to reorder step 5
DISPATCH YARD
5. Stillage Sequenc…
×2
FIFO Lane
C/T
7.5 min
C/O
10 min
Availability
97%
Quality FPY
99.1%
Batch / EPEI
16 / 1d
OEE
91.8%
i
Insert a step at the end
+
I
52
0.80 d
Finished Goods
OUT
1.40 d
VA 9.0 min
1.20 d
VA 10.0 min
2.00 d
VA 14.8 min
1.00 d
VA 11.1 min
0.60 d
VA 7.5 min
0.80 d
Total Lead Time
7.06 d
VA Time
52.4 min
PCE
0.82%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step