Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Offsite Prefabricated Tiled Bathroom Wet-Pod
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
32.1 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
7.14 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
2.0 h
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
1.89%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Board Sheath, Tile & Grout
19 < 28/day
Limit: downtime
Board Sheath, Tile & Grout: capacity 19/day vs demand 28/day. Main limit: downtime. Raw C/T 34.4 min, effective C/T 43.0 min.
Quality (RTY)
85.9%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€666,400
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
81.3 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Sanitary Fittings & C…
Steel Studs, Waterproof…
Weekly Steel/MEP · LT 8d
PRODUCTION CONTROL / ERP
PodMES
Project Job-Shop Push
CUSTOMER
Multi-Family & Hotel …
28 modules/d
Takt: 32.1 min
EDI / Daily Crane Slot
MRP / Weekly Steel/MEP
★ PACEMAKER
IN
Insert a step at the start
+
I
39
1.39 d
Drag to reorder step 1
BAY 1 FRAME
1. GRC Waterproof B…
×4
Push Flow
C/T
20.9 min
C/O
35 min
Availability
93%
Quality FPY
98.2%
Batch / EPEI
22 / 2d
OEE
86.8%
i
Insert a step here
+
I
34
1.21 d
Drag to reorder step 2
BAY 2 SHELL
2. Steel Frame & Pl…
×4
Push Flow
C/T
23.2 min
C/O
20 min
Availability
94%
Quality FPY
97.6%
Batch / EPEI
14 / 1d
OEE
87.7%
i
Insert a step here
+
I
56
2.00 d
BALANCING
Pre-Built…
Drag to reorder step 3
BAY 3 MEP
3. Board Sheath, Ti…
×5
BOTTLENECK
C/T
34.4 min
C/O
30 min
Availability
86%
Quality FPY
93.0%
Batch / EPEI
11 / 1d
OEE
73.2%
i
Insert a step here
+
I
28
1.00 d
Drag to reorder step 4
BAY 4 FINISH
4. Vanity, Mirror, …
×4
FIFO Lane
C/T
25.7 min
C/O
15 min
Availability
94%
Quality FPY
97.2%
Batch / EPEI
8 / 1d
OEE
86.0%
i
FIFO
Insert a step here
+
I
17
0.61 d
Drag to reorder step 5
DISPATCH YARD
5. 3-Bar Leak Test …
×2
FIFO Lane
C/T
17.4 min
C/O
10 min
Availability
97%
Quality FPY
99.1%
Batch / EPEI
7 / 1d
OEE
91.9%
i
Insert a step at the end
+
I
22
0.79 d
Finished Goods
OUT
1.39 d
VA 20.9 min
1.21 d
VA 23.2 min
2.00 d
VA 34.4 min
1.00 d
VA 25.7 min
0.61 d
VA 17.4 min
0.79 d
Total Lead Time
7.14 d
VA Time
2.0 h
PCE
1.89%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step