Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Factory SMR Nuclear Heat Exchanger Coil Module
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
7.5 h
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
9.39 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
28.4 h
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
20.13%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
100% Helium Mass-Spec Scan
1 < 2/day
Limit: downtime
100% Helium Mass-Spec Scan: capacity 1/day vs demand 2/day. Main limit: downtime. Raw C/T 8.0 h, effective C/T 10.3 h.
Quality (RTY)
84.4%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€1,110,000
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
2.4 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Alloy 690 Seamless Tu…
Foraged Nuclear Tube Sh…
Weekly · LT 9d
PRODUCTION CONTROL / ERP
NQA-1 MES
Milestone Batch Release
CUSTOMER
Next-Gen Clean Nuclear
2 modules/d
Takt: 7.5 h
EDI / Daily Low-Loader
MRP / Weekly
★ PACEMAKER
IN
Insert a step at the start
+
I
3
1.50 d
Drag to reorder step 1
YARD STAGING
1. Cleanroom Alloy-…
×3
Push Flow
C/T
4.9 h
C/O
20 min
Availability
94%
Quality FPY
98.5%
Batch / EPEI
2 / 2d
OEE
90.5%
i
Insert a step here
+
I
3
1.50 d
Drag to reorder step 2
ELECTRICAL FIELD
2. Robot TIG Tube-t…
×4
Push Flow
C/T
6.0 h
C/O
25 min
Availability
91%
Quality FPY
96.4%
Batch / EPEI
2 / 2d
OEE
85.3%
i
Insert a step here
+
I
4
2.00 d
QUALITY
Factory H…
Drag to reorder step 3
HV TESTING
3. 100% Helium Mass…
×3
BOTTLENECK
C/T
8.0 h
C/O
45 min
Availability
85%
Quality FPY
92.0%
Batch / EPEI
1 / 2d
OEE
76.2%
i
Insert a step here
+
I
2
1.00 d
Drag to reorder step 4
GRID COMPLIANCE
4. ASME Sec-III Hyd…
×2
FIFO Lane
C/T
5.6 h
C/O
15 min
Availability
95%
Quality FPY
97.5%
Batch / EPEI
1 / 1d
OEE
91.1%
i
FIFO
Insert a step here
+
I
1
0.50 d
Drag to reorder step 5
GRID SIGN-OFF
5. Heavy Skid Nitro…
×2
Continuous Flow
C/T
3.9 h
C/O
8 min
Availability
97%
Quality FPY
99.1%
Batch / EPEI
1 / 1d
OEE
95.3%
i
Insert a step at the end
+
I
2
1.00 d
Finished Goods
OUT
1.50 d
VA 4.9 h
1.50 d
VA 6.0 h
2.00 d
VA 8.0 h
1.00 d
VA 5.6 h
0.50 d
VA 3.9 h
1.00 d
Total Lead Time
9.39 d
VA Time
28.4 h
PCE
20.13%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step