Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Vacuum Sublimation Freeze-Dried Strawberry Line
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
5.7 s
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
8.00 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
22 s
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.01%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Low-RH <10% Dry Nitrogen Room
6,716 < 9,500/day
Limit: downtime
Low-RH <10% Dry Nitrogen Room: capacity 6,716/day vs demand 9,500/day. Main limit: downtime. Raw C/T 6.1 s, effective C/T 7.5 s.
Quality (RTY)
91.1%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€144,400
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
1,517.3 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
IQF Berry Cold Farms
Pre-Sliced IQF Strawber…
2x / week · LT 4d
PRODUCTION CONTROL / ERP
ERP
Allergen Campaign Push
CUSTOMER
Snacking & Cereal Co-…
9,500 packs/d
Takt: 5.7 s
EDI / Daily Frozen/Dry
MRP / 2x / week
★ PACEMAKER
IN
Insert a step at the start
+
I
10,450
1.10 d
Drag to reorder step 1
KITCHEN PREP
1. Frozen Tray Load…
×3
Push Flow
C/T
3.9 s
C/O
25 min
Availability
95%
Quality FPY
98.8%
Batch / EPEI
7600 / 1d
OEE
90.6%
i
Insert a step here
+
I
12,350
1.30 d
Drag to reorder step 2
THERMAL BLOCK
2. -45°C Vacuum Fre…
×2
Push Flow
C/T
4.8 s
C/O
40 min
Availability
90%
Quality FPY
97.5%
Batch / EPEI
7600 / 2d
OEE
82.9%
i
Insert a step here
+
I
17,100
1.80 d
FLOW
Rotary Re…
Drag to reorder step 3
RETORT/PACK
3. Low-RH <10% Dry …
×2
BOTTLENECK
C/T
6.1 s
C/O
55 min
Availability
84%
Quality FPY
96.2%
Batch / EPEI
9500 / 2d
OEE
75.9%
i
Insert a step here
+
I
7,600
0.80 d
Drag to reorder step 4
FOOD SAFETY
4. Metal Screen & R…
×1
FIFO Lane
C/T
4.1 s
C/O
8 min
Availability
96%
Quality FPY
98.9%
Batch / EPEI
2850 / 1d
OEE
92.1%
i
FIFO
Insert a step here
+
I
11,400
1.20 d
Drag to reorder step 5
FROZEN DOCK
5. O2-Scavenger Ins…
×2
FIFO Lane
C/T
3.3 s
C/O
10 min
Availability
97%
Quality FPY
99.4%
Batch / EPEI
2850 / 1d
OEE
92.8%
i
Insert a step at the end
+
I
17,100
1.80 d
Finished Goods
OUT
1.10 d
VA 3.9 s
1.30 d
VA 4.8 s
1.80 d
VA 6.1 s
0.80 d
VA 4.1 s
1.20 d
VA 3.3 s
1.80 d
Total Lead Time
8.00 d
VA Time
22 s
PCE
0.01%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step