63kV Overhead Aluminum HTLS Reconductoring
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
37.5 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
7.73 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
2.4 h
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
4.07%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Tensioner Dead-End Compress
7 < 12/day
Limit: changeovers
Tensioner Dead-End Compress: capacity 7/day vs demand 12/day. Main limit: changeovers. Raw C/T 40.5 min, effective C/T 50.4 min.
Quality (RTY)
85.9%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€747,600
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
9.7 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Composite-Core Carbon…
Stringing Rollers & Pul…
Weekly Depot Pull · LT 6d
PRODUCTION CONTROL / ERP
LineOps ERP
Network Outage Window Queue
CUSTOMER
Regional Distribution…
12 cases/d
Takt: 37.5 min
EDI / Energized Bay
MRP / Weekly Depot Pull
★ PACEMAKER
IN
Insert a step at the start
+
I
22
1.83 d
Drag to reorder step 1
GRID DISPATCH
1. Line Outage & Ea…
×2
Push Flow
C/T
24.8 min
C/O
15 min
Availability
96%
Quality FPY
95.8%
Batch / EPEI
4 / 1d
OEE
82.8%
i
Insert a step here
+
I
19
1.58 d
Drag to reorder step 2
CIVIL FIELD
2. Drone Pilot Line…
×4
Push Flow
C/T
29.3 min
C/O
20 min
Availability
93%
Quality FPY
97.6%
Batch / EPEI
5 / 1d
OEE
81.1%
i
Insert a step here
+
I
26
2.17 d
SMED
Mobile Su…
Drag to reorder step 3
HV CREW
3. Tensioner Dead-E…
×5
BOTTLENECK
C/T
40.5 min
C/O
30 min
Availability
85%
Quality FPY
94.5%
Batch / EPEI
4 / 1d
OEE
64.3%
i
Insert a step here
+
I
11
0.92 d
Drag to reorder step 4
PROTECTION LAB
4. Sag Check Laser …
×2
FIFO Lane
C/T
28.5 min
C/O
12 min
Availability
94%
Quality FPY
97.8%
Batch / EPEI
2 / 1d
OEE
77.2%
i
FIFO
Insert a step here
+
I
5
0.42 d
Drag to reorder step 5
CONTROL CENTER
5. Helicopter Coron…
×1
Continuous Flow
C/T
18.8 min
C/O
5 min
Availability
98%
Quality FPY
99.4%
Batch / EPEI
1 / 1d
OEE
96.3%
i
Insert a step at the end
+
I
6
0.50 d
Finished Goods
OUT
1.83 d
VA 24.8 min
1.58 d
VA 29.3 min
2.17 d
VA 40.5 min
0.92 d
VA 28.5 min
0.42 d
VA 18.8 min
0.50 d
Total Lead Time
7.73 d
VA Time
2.4 h
PCE
4.07%