Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Pre-Loaded C3 Precision Ground Ball Screw
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
2.8 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
10.7 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
11.1 min
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.12%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Ball Nut Internal Pitch Grind
232 < 320/day
Limit: downtime
Ball Nut Internal Pitch Grind: capacity 232/day vs demand 320/day. Main limit: downtime. Raw C/T 3.0 min, effective C/T 3.7 min.
Quality (RTY)
90.8%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€719,040
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
31.6 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Bearing-steel bar sup…
Induction Hardened Shaf…
Weekly Rod Coil · LT 6d
PRODUCTION CONTROL / ERP
Production ERP
Campaign Heat-Treat Push
CUSTOMER
Machine Tool & Roboti…
320 units/d
Takt: 2.8 min
EDI / Daily Pallet
MRP / Weekly Rod Coil
★ PACEMAKER
IN
Insert a step at the start
+
I
704
2.20 d
Drag to reorder step 1
HEADER LINE
1. Induction Thread…
×2
Push Flow
C/T
2.0 min
C/O
65 min
Availability
90%
Quality FPY
98.8%
Batch / EPEI
640 / 3d
OEE
85.7%
i
Insert a step here
+
I
576
1.80 d
Drag to reorder step 2
TOOTH/THREAD
2. Laser-Guided Thr…
×2
Push Flow
C/T
2.4 min
C/O
45 min
Availability
91%
Quality FPY
97.6%
Batch / EPEI
480 / 2d
OEE
85.9%
i
Insert a step here
+
I
768
2.40 d
FLOW
Pull Cell…
Drag to reorder step 3
HEAT/GRIND
3. Ball Nut Interna…
×2
BOTTLENECK
C/T
3.0 min
C/O
50 min
Availability
84%
Quality FPY
96.1%
Batch / EPEI
480 / 3d
OEE
77.7%
i
Insert a step here
+
I
480
1.50 d
Drag to reorder step 4
PLATING BAY
4. Selective Steel …
×2
Push Flow
C/T
2.1 min
C/O
20 min
Availability
93%
Quality FPY
98.4%
Batch / EPEI
320 / 2d
OEE
89.5%
i
Insert a step here
+
I
256
0.80 d
Drag to reorder step 5
AUTO PACK
5. Laser Pitch Erro…
×1
FIFO Lane
C/T
95 s
C/O
12 min
Availability
97%
Quality FPY
99.6%
Batch / EPEI
160 / 1d
OEE
94.0%
i
Insert a step at the end
+
I
640
2.00 d
Finished Goods
OUT
2.20 d
VA 2.0 min
1.80 d
VA 2.4 min
2.40 d
VA 3.0 min
1.50 d
VA 2.1 min
0.80 d
VA 95 s
2.00 d
Total Lead Time
10.7 d
VA Time
11.1 min
PCE
0.12%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step