Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
High-Volume Metal Binder-Jet 3D Print Line
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
85 s
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
8.20 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
5.6 min
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.05%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Debind & Vacuum Sinter Profile
685 < 950/day
Limit: downtime
Debind & Vacuum Sinter Profile: capacity 685/day vs demand 950/day. Main limit: downtime. Raw C/T 91 s, effective C/T 113 s.
Quality (RTY)
88.1%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€218,120
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
574.3 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
MIM powder supplier
10um Stainless Metal Po…
Weekly · LT 9d
PRODUCTION CONTROL / ERP
Additive MES
Order Build Slot
CUSTOMER
Automotive & Consumer…
950 parts/d
Takt: 85 s
EDI / Custom Crating
MRP / Weekly
★ PACEMAKER
IN
Insert a step at the start
+
I
1,710
1.80 d
Drag to reorder step 1
PARTS PREP
1. Binder-Jet Piezo…
×2
Push Flow
C/T
60 s
C/O
25 min
Availability
94%
Quality FPY
98.4%
Batch / EPEI
760 / 2d
OEE
90.4%
i
Insert a step here
+
I
1,425
1.50 d
Drag to reorder step 2
JOINT CELL
2. Thermal Cure Dep…
×3
Push Flow
C/T
72 s
C/O
20 min
Availability
92%
Quality FPY
97.2%
Batch / EPEI
380 / 1d
OEE
86.1%
i
Insert a step here
+
I
1,900
2.00 d
AUTOMATION
Multi-Bay…
Drag to reorder step 3
LASER BAY
3. Debind & Vacuum …
×3
BOTTLENECK
C/T
91 s
C/O
30 min
Availability
85%
Quality FPY
94.8%
Batch / EPEI
475 / 1d
OEE
77.0%
i
Insert a step here
+
I
950
1.00 d
Drag to reorder step 4
CONTROL RACK
4. Automated Tumbli…
×2
FIFO Lane
C/T
65 s
C/O
12 min
Availability
95%
Quality FPY
98.0%
Batch / EPEI
238 / 1d
OEE
89.8%
i
FIFO
Insert a step here
+
I
665
0.70 d
Drag to reorder step 5
CERT PACK
5. Archimedes Densi…
×2
Continuous Flow
C/T
49 s
C/O
10 min
Availability
97%
Quality FPY
99.1%
Batch / EPEI
143 / 1d
OEE
91.4%
i
Insert a step at the end
+
I
1,140
1.20 d
Finished Goods
OUT
1.80 d
VA 60 s
1.50 d
VA 72 s
2.00 d
VA 91 s
1.00 d
VA 65 s
0.70 d
VA 49 s
1.20 d
Total Lead Time
8.20 d
VA Time
5.6 min
PCE
0.05%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen