Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Compact Brushless Industrial Servo Motor
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
87 s
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
9.11 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
5.8 min
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.07%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
N42SH Magnet Rotor Banding
438 < 620/day
Limit: downtime
N42SH Magnet Rotor Banding: capacity 438/day vs demand 620/day. Main limit: downtime. Raw C/T 94 s, effective C/T 117 s.
Quality (RTY)
89.0%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€1,636,180
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
189.1 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
NdFeB magnet supplier
Si-Steel Stators & Enam…
2x / week · LT 5d
PRODUCTION CONTROL / ERP
Manufacturing ERP
Batch Bake Queue Push
CUSTOMER
Packaging & CNC OEMs
620 units/d
Takt: 87 s
EDI / Daily Truck
MRP / 2x / week
★ PACEMAKER
IN
Insert a step at the start
+
I
1,054
1.70 d
Drag to reorder step 1
COIL/STAMP
1. Segmented Stator…
×2
Push Flow
C/T
59 s
C/O
35 min
Availability
93%
Quality FPY
98.7%
Batch / EPEI
930 / 2d
OEE
89.4%
i
Insert a step here
+
I
1,116
1.80 d
Drag to reorder step 2
WINDING HALL
2. Trickle Resin Cu…
×3
Push Flow
C/T
75 s
C/O
30 min
Availability
90%
Quality FPY
96.9%
Batch / EPEI
496 / 2d
OEE
83.6%
i
Insert a step here
+
I
1,364
2.20 d
SMED
Trickle U…
Drag to reorder step 3
THERMAL CELL
3. N42SH Magnet Rot…
×3
BOTTLENECK
C/T
94 s
C/O
45 min
Availability
84%
Quality FPY
95.5%
Batch / EPEI
620 / 2d
OEE
76.2%
i
Insert a step here
+
I
682
1.10 d
Drag to reorder step 4
ASSEMBLY BAY
4. 24-Bit Absolute …
×3
FIFO Lane
C/T
68 s
C/O
15 min
Availability
94%
Quality FPY
98.3%
Batch / EPEI
248 / 1d
OEE
88.6%
i
FIFO
Insert a step here
+
I
496
0.80 d
Drag to reorder step 5
EOL QC
5. Torque-Ripple Ba…
×2
Continuous Flow
C/T
52 s
C/O
8 min
Availability
96%
Quality FPY
99.1%
Batch / EPEI
124 / 1d
OEE
90.9%
i
Insert a step at the end
+
I
930
1.50 d
Finished Goods
OUT
1.70 d
VA 59 s
1.80 d
VA 75 s
2.20 d
VA 94 s
1.10 d
VA 68 s
0.80 d
VA 52 s
1.50 d
Total Lead Time
9.11 d
VA Time
5.8 min
PCE
0.07%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen