Vertical Twin-Shaft Regenerative Quicklime Kiln
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
2.6 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
7.11 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
9.7 min
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.10%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
PFR Twin-Shaft 1100°C Calciner
384 < 520/day
Limit: downtime
PFR Twin-Shaft 1100°C Calciner: capacity 384/day vs demand 520/day. Main limit: downtime. Raw C/T 2.8 min, effective C/T 3.4 min.
Quality (RTY)
92.4%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€387,660
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
4,864.2 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
High-Purity Calcium Q…
40–80mm Crushed Limesto…
Daily Conveyor · LT 2d
PRODUCTION CONTROL / ERP
LimeERP
Batch Kiln & Silo Hold
CUSTOMER
Steel Mills, Water & …
520 tonnes/d
Takt: 2.6 min
EDI / Continuous Mixer
MRP / Daily Conveyor
★ PACEMAKER
IN
Insert a step at the start
+
I
728
1.40 d
Drag to reorder step 1
RAW PREP
1. Wash Screen & Sk…
×2
Continuous Flow
C/T
100 s
C/O
20 min
Availability
95%
Quality FPY
99.1%
Batch / EPEI
624 / 2d
OEE
93.0%
i
Insert a step here
+
I
936
1.80 d
GREEN
Alternati…
Drag to reorder step 2
PYRO LINE
2. PFR Twin-Shaft 1…
×2
BOTTLENECK
C/T
2.8 min
C/O
45 min
Availability
84%
Quality FPY
96.4%
Batch / EPEI
780 / 3d
OEE
79.2%
i
Insert a step here
+
I
624
1.20 d
Drag to reorder step 3
MILL/MIXER
3. Hydrator Slaking…
×2
Push Flow
C/T
2.1 min
C/O
15 min
Availability
93%
Quality FPY
98.4%
Batch / EPEI
416 / 1d
OEE
90.2%
i
Insert a step here
+
I
364
0.70 d
Drag to reorder step 4
CEMENT LAB
4. Silica-Free Siev…
×1
FIFO Lane
C/T
106 s
C/O
5 min
Availability
96%
Quality FPY
98.8%
Batch / EPEI
156 / 1d
OEE
93.7%
i
FIFO
Insert a step here
+
I
416
0.80 d
Drag to reorder step 5
WEIGHBRIDGE
5. Bulk Silo & Pneu…
×2
FIFO Lane
C/T
81 s
C/O
8 min
Availability
97%
Quality FPY
99.5%
Batch / EPEI
130 / 1d
OEE
94.2%
i
Insert a step at the end
+
I
624
1.20 d
Finished Goods
OUT
1.40 d
VA 100 s
1.80 d
VA 2.8 min
1.20 d
VA 2.1 min
0.70 d
VA 106 s
0.80 d
VA 81 s
1.20 d
Total Lead Time
7.11 d
VA Time
9.7 min
PCE
0.10%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step