Pick a template or start a blank map, then edit cycle times and watch the bottleneck move.
VSME
.net
/
Granular Muriate of Potash (MOP) Compaction
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
2.6 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
8.81 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
10.1 min
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
0.09%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
Smooth-Roll High-Force Flake
361 < 520/day
Limit: downtime
Smooth-Roll High-Force Flake: capacity 361/day vs demand 520/day. Main limit: downtime. Raw C/T 2.8 min, effective C/T 3.6 min.
Quality (RTY)
89.2%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€960,960
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
2,647.0 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
Underground Room-and-…
Flotation KCl Fines
Continuous Pit · LT 1d
PRODUCTION CONTROL / ERP
PotashERP
Uncontrolled ROM Stockpile Push
CUSTOMER
Bulk NPK Blending Ter…
520 tonnes/d
Takt: 2.6 min
EDI / Daily Block Train
MRP / Continuous Pit
★ PACEMAKER
IN
Insert a step at the start
+
I
728
1.40 d
Drag to reorder step 1
OPEN PIT
1. Dry Screw Feeder…
×4
FIFO Lane
C/T
112 s
C/O
10 min
Availability
92%
Quality FPY
98.8%
Batch / EPEI
520 / 1d
OEE
90.2%
i
FIFO
Insert a step here
+
I
1,144
2.20 d
TPM
TPM Vibra…
Drag to reorder step 2
COMMINUTION
2. Smooth-Roll High…
×3
BOTTLENECK
C/T
2.8 min
C/O
35 min
Availability
81%
Quality FPY
95.0%
Batch / EPEI
520 / 1d
OEE
75.0%
i
Insert a step here
+
I
832
1.60 d
Drag to reorder step 3
BENEFICIATION
3. Crusher & Double…
×3
Continuous Flow
C/T
2.2 min
C/O
20 min
Availability
91%
Quality FPY
97.2%
Batch / EPEI
416 / 2d
OEE
86.8%
i
Insert a step here
+
I
520
1.00 d
Drag to reorder step 4
ASSAY LAB
4. Glazing Drum Ste…
×2
FIFO Lane
C/T
109 s
C/O
10 min
Availability
95%
Quality FPY
98.4%
Batch / EPEI
208 / 1d
OEE
91.7%
i
FIFO
Insert a step here
+
I
624
1.20 d
Drag to reorder step 5
BULK DISPATCH
5. Bulk Covered Hop…
×2
FIFO Lane
C/T
87 s
C/O
8 min
Availability
97%
Quality FPY
99.4%
Batch / EPEI
208 / 1d
OEE
95.0%
i
Insert a step at the end
+
I
728
1.40 d
Finished Goods
OUT
1.40 d
VA 112 s
2.20 d
VA 2.8 min
1.60 d
VA 2.2 min
1.00 d
VA 109 s
1.20 d
VA 87 s
1.40 d
Total Lead Time
8.81 d
VA Time
10.1 min
PCE
0.09%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen