Utility Solar PV Skid & Grid Commissioning
Current State
Create Future State
Blueprints
Smart Advisor
Export
EN
VSM Map
Yamazumi & Pareto
Simulation & Pull
OpEx Suite
Before / After ROI
Data & Excel
Current State
Optimize Flow
Takt Time
30.0 min
Takt time = available time per day ÷ customer demand per day: the pace at which the customer buys.
Lead Time (LT)
7.99 d
Lead time = total time a unit spends in the flow: waiting in stock (stock ÷ daily demand) plus processing.
Value-Added
1.9 h
Value-added time = sum of the cycle times of all steps: the time actually spent transforming the product.
Efficiency (PCE)
3.16%
Process cycle efficiency = value-added time ÷ lead time. Both are counted in available production time (shift time less breaks), not in calendar time.
Bottleneck
HV Inverter Commissioning
9 < 15/day
Limit: changeovers
HV Inverter Commissioning: capacity 9/day vs demand 15/day. Main limit: changeovers. Raw C/T 32.1 min, effective C/T 41.0 min.
Quality (RTY)
84.4%
Rolled throughput yield = product of the first-pass yields of all steps: the share of units right first time.
WIP Capital
€556,800
Working capital tied up in stock: units in buffers and finished goods × unit cost.
Carbon CO₂
18.3 t CO₂e/year
Blank Value Stream (Free)
1,080 Industry Templates (Free)
Generate with AI
Sign In · 5 Free AI Credits
VSME.net · ISO 22468 Value Stream Map · Current State
SUPPLIER
PV Tier-1 & Transform…
Modules, Inverters & MV…
Weekly · LT 9d
PRODUCTION CONTROL / ERP
EPC Scheduling + ERP
Milestone Batch Release
CUSTOMER
Utility Grid Operators
15 skids/d
Takt: 30.0 min
EDI / Daily Low-Loader
MRP / Weekly
★ PACEMAKER
IN
Insert a step at the start
+
I
24
1.60 d
Drag to reorder step 1
YARD STAGING
1. Structure Kitting
×3
Push Flow
C/T
19.5 min
C/O
20 min
Availability
94%
Quality FPY
98.5%
Batch / EPEI
15 / 2d
OEE
88.5%
i
Insert a step here
+
I
23
1.53 d
Drag to reorder step 2
ELECTRICAL FIELD
2. DC Array Wiring
×4
Push Flow
C/T
24.0 min
C/O
25 min
Availability
91%
Quality FPY
96.4%
Batch / EPEI
12 / 2d
OEE
81.6%
i
Insert a step here
+
I
33
2.20 d
QUALITY
Factory H…
Drag to reorder step 3
HV TESTING
3. HV Inverter Comm…
×3
BOTTLENECK
C/T
32.1 min
C/O
45 min
Availability
85%
Quality FPY
92.0%
Batch / EPEI
9 / 2d
OEE
65.2%
i
Insert a step here
+
I
15
1.00 d
Drag to reorder step 4
GRID COMPLIANCE
4. SCADA Grid Sync
×2
FIFO Lane
C/T
22.2 min
C/O
15 min
Availability
95%
Quality FPY
97.5%
Batch / EPEI
6 / 1d
OEE
84.9%
i
FIFO
Insert a step here
+
I
9
0.60 d
Drag to reorder step 5
GRID SIGN-OFF
5. Utility Energize…
×2
Continuous Flow
C/T
15.6 min
C/O
8 min
Availability
97%
Quality FPY
99.1%
Batch / EPEI
3 / 1d
OEE
87.6%
i
Insert a step at the end
+
I
12
0.80 d
Finished Goods
OUT
1.60 d
VA 19.5 min
1.53 d
VA 24.0 min
2.20 d
VA 32.1 min
1.00 d
VA 22.2 min
0.60 d
VA 15.6 min
0.80 d
Total Lead Time
7.99 d
VA Time
1.9 h
PCE
3.16%
Drag the background (or hold Space) to pan · Ctrl+scroll to zoom · drag a step header to reorder · F for full screen
90%
100%
Fit
Full screen
Dark Blueprint
Info Flows
Kaizen
Green CO₂
Add step