Kanban Card Calculator
A kanban loop holds enough stock to cover demand during the replenishment lead time, plus a safety margin. Dividing that stock by the container size gives the number of cards to put in the loop.
Free to use, no account. The calculation uses the same functions as the editor, so both always give the same figures.
Inputs
Formula and units
- Consumption during lead time = D × LT
- Safety stock = ⌈D × LT × SS⌉
- Units in the loop = ⌈D × LT + safety stock⌉
- Cards K = ⌈units in the loop ÷ Q⌉ (at least 1)
D in units per day, LT in days (at least 0.15, like the editor), SS as a fraction (20 % = 0.2), Q in units per container. ⌈ ⌉ rounds up.
Worked example
Example values
- Daily demand (units per day)
- 1,200
- Replenishment lead time (days)
- 0.5
- Safety factor (%)
- 20
- Units per container
- 50
Result
- Consumption during lead time
- 600.0
- Safety stock
- 120
- Units in the loop
- 720
- Kanban cards
- 15
The loop needs 15 Kanban cards.