Automotive Electromechanical Assembly

Product family: Chassis Actuator Module.

Flow: Steel & sensor component supplier → Stamping Press → Robotic Welding → Surface Coating → Final Assembly → EOL Functional Test → OEM Vehicle Assembly Plant

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Automotive Electromechanical AssemblySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Steel & sensor component supplier → Stamping Press (39.9 s) → Robotic Welding (49.0 s) → Surface Coating (53.0 s) → Final Assembly (63.0 s) → EOL Functional Test (42.0 s) → OEM Vehicle Assembly Plant.SUPPLIERSteel & sensorcomponentsupplierI2.40 d1Stamping PressC/T 39.9 sI1.80 d2Robotic WeldingC/T 49.0 sI1.90 d3Surface CoatingC/T 53.0 sI1.60 d4Final AssemblyC/T 63.0 sI0.80 d5EOL FunctionalTestC/T 42.0 sI1.50 dCUSTOMEROEM VehicleAssembly Plant920 / modules

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Stamping Press39.9 s75 min88%98.5%1,8402,208 (2.40 d)1,124
2. Robotic Welding49.0 s35 min90%97.4%7361,656 (1.80 d)919
3. Surface Coating53.0 s40 min91%97.9%9201,748 (1.90 d)867
4. Final Assembly63.0 s18 min86%95.8%2761,472 (1.60 d)659
5. EOL Functional Test42.0 s12 min95%98.9%138736 (0.80 d)1,101

Key figures

Takt time
58.7 s
Lead time
10.0 d
Value-added time
247 s
Process cycle efficiency (PCE)
0.046%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
920 modules
Line capacity per day
659 modules
Bottleneck
Final Assembly

Reading the bottleneck

The bottleneck is "Final Assembly": it can process 659 modules per day against a demand of 920 modules, so it falls short of demand by 28.4%. Once downtime and scrap are counted, its cycle time grows from 63.0 s to 76.5 s, against a takt of 58.7 s. The largest loss at this step is equipment downtime (uptime 86%), about 10.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of BIW Stamping & Electromechanical: BIW Stamping & Electromechanical