Lead Time and PCE Calculator

Lead time is the total time a unit spends in the process, waiting included. Process cycle efficiency (PCE) is the share of that time spent actually working on the product, usually small, which is why waiting is where the gains are.

Free to use, no account. The calculation uses the same functions as the editor, so both always give the same figures.

Inputs

  1. Step 1

  2. Step 2

  3. Step 3

  4. Step 4

Result

Value-added time
145 s
Waiting time
6.00 d
Lead time
6.01 d
PCE
0.084%

Formula and units

  • Value-added time (s) = sum of the cycle times
  • Lead time (days) = (value-added time + waiting time) ÷ available time per day
  • Waiting time = sum of the stock before each step and in finished goods, in days of demand
  • PCE (%) = value-added time ÷ lead time × 100

Stock is entered in days of demand, converted to units with the daily demand. Days are days of available production time.

Worked example

Example values

Customer demand (units per day)
1,000
Available hours per day
8
1. Cycle time (s) / Wait before the step (days)
40 / 2.0
2. Cycle time (s) / Wait before the step (days)
55 / 1.5
3. Cycle time (s) / Wait before the step (days)
30 / 1.0
4. Cycle time (s) / Wait before the step (days)
20 / 0.5
Finished goods stock (days)
1.0

Result

Value-added time
145 s
Waiting time
6.00 d
Lead time
6.01 d
PCE
0.084%

The unit spends 6.01 d (PCE 0.084%) in the process.