UHT Aseptic Dairy Processing & Filling
Product family: 1L UHT Aseptic Bricks.
Flow: Dairy Co-op & Carton Supplier → Reception & Standardization → Homogenize & Cream Balance → UHT Sterilizer & CIP Cycles → Aseptic Brick Filling → Tray Wrap & Cold Store → Supermarket Regional Hubs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Reception & Standardization | 4.5 s | 25 min | 95% | 99.1% | 8,000 | 9,600 (1.20 d) | 10,984 |
| 2. Homogenize & Cream Balance | 5.4 s | 35 min | 92% | 98.4% | 6,400 | 8,800 (1.10 d) | 8,613 |
| 3. UHT Sterilizer & CIP Cycles | 7.2 s | 85 min | 81% | 97.5% | 8,000 | 12,000 (1.50 d) | 5,364 |
| 4. Aseptic Brick Filling | 5.7 s | 30 min | 90% | 97.9% | 4,000 | 7,200 (0.90 d) | 7,791 |
| 5. Tray Wrap & Cold Store | 4.2 s | 12 min | 96% | 99.4% | 3,200 | 8,800 (1.10 d) | 11,860 |
Key figures
- Takt time
- 6.8 s
- Lead time
- 7.20 d
- Value-added time
- 27.0 s
- Process cycle efficiency (PCE)
- 0.007%
- Rolled throughput yield (RTY)
- 92.5%
- Customer demand per day
- 8,000 packs
- Line capacity per day
- 5,364 packs
- Bottleneck
- UHT Sterilizer & CIP Cycles
Reading the bottleneck
The bottleneck is "UHT Sterilizer & CIP Cycles": it can process 5,364 packs per day against a demand of 8,000 packs, so it falls short of demand by 33.0%. Once downtime and scrap are counted, its cycle time grows from 7.2 s to 9.1 s, against a takt of 6.8 s. The largest loss at this step is equipment downtime (uptime 81%), about 1.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Dairy, UHT & Plant-Based Alt: Dairy, UHT & Plant-Based Alt
- Ultrafiltered Stirred Greek Yogurt Cup Line
- Continuous Pasta-Filata Mozzarella Shred & Ball
- Enzymatic Oat Hydrolysis UHT Plant-Milk Line
- GMP Stage-1 Spray-Dried Infant Formula Can Line
- Rotary Extruded Chocolate-Dipped Ice Cream Bar
- Microfiltered Whey Isolate (WPI) Pouch & Tub Line
- Continuous Churn Cultured Butter Parchment Wrap
- Traditional Soft Surface-Ripened Cheese Flow
- Live 12-Strain Cultured Kefir PET Bottle
- Vacuum Evaporated Sweetened Condensed Milk Can
- Coconut-Starch Plant-Based Sliced Cheese Line