OEE Calculator
Overall equipment effectiveness (OEE) shows how much of the planned time a machine produces good parts at its ideal speed. It multiplies three losses: availability, performance and quality.
Free to use, no account. The calculation uses the same functions as the editor, so both always give the same figures.
Inputs
Formula and units
- Availability = (planned time − downtime) ÷ planned time
- Performance = ideal cycle time × total units ÷ run time (capped at 100 %)
- Quality = good units ÷ total units
- OEE = availability × performance × quality
Times in minutes, ideal cycle time in seconds per unit. Result in percent.
Worked example
Example values
- Planned production time (minutes)
- 480
- Downtime (minutes)
- 60
- Ideal cycle time (seconds per unit)
- 30
- Total units produced
- 750
- Good units
- 720
Result
- Run time
- 420 min
- Availability
- 87.5%
- Performance
- 89.3%
- Quality
- 96.0%
- OEE
- 75.0%
Multiplying the three factors gives an OEE of 75.0%.