PCB SMT Pick-and-Place & Box Build

Product family: Industrial IoT Controller Boards.

Flow: EMS Silicon & PCB Distributors → Solder Paste Print & SPI → SMD Pick & Place → Reflow Oven & 3D AOI → Selective Wave Soldering → ICT & Box-Build Pack → Industrial OEM Clients

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: PCB SMT Pick-and-Place & Box BuildSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. EMS Silicon & PCB Distributors → Solder Paste Print & SPI (12.6 s) → SMD Pick & Place (18.4 s) → Reflow Oven & 3D AOI (24.1 s) → Selective Wave Soldering (17.6 s) → ICT & Box-Build Pack (15.3 s) → Industrial OEM Clients.SUPPLIEREMS Silicon &PCBDistributorsI1.20 d1Solder PastePrint & SPIC/T 12.6 sI1.40 d2SMD Pick & PlaceC/T 18.4 sI1.80 d3Reflow Oven & 3DAOIC/T 24.1 sI1.00 d4Selective WaveSolderingC/T 17.6 sI0.80 d5ICT & Box-BuildPackC/T 15.3 sI1.20 dCUSTOMERIndustrial OEMClients2,400 / boards

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Solder Paste Print & SPI12.6 s25 min95%98.6%1,9202,880 (1.20 d)3,875
2. SMD Pick & Place18.4 s35 min91%97.4%1,9203,360 (1.40 d)2,475
3. Reflow Oven & 3D AOI24.1 s45 min84%95.4%2,4004,320 (1.80 d)1,706
4. Selective Wave Soldering17.6 s18 min93%98.1%9602,400 (1.00 d)2,659
5. ICT & Box-Build Pack15.3 s15 min95%98.8%6001,920 (0.80 d)3,092

Key figures

Takt time
22.5 s
Lead time
7.40 d
Value-added time
88.0 s
Process cycle efficiency (PCE)
0.022%
Rolled throughput yield (RTY)
88.8%
Customer demand per day
2,400 boards
Line capacity per day
1,706 boards
Bottleneck
Reflow Oven & 3D AOI

Reading the bottleneck

The bottleneck is "Reflow Oven & 3D AOI": it can process 1,706 boards per day against a demand of 2,400 boards, so it falls short of demand by 28.9%. Once downtime and scrap are counted, its cycle time grows from 24.1 s to 30.1 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 4.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.