PCB SMT Pick-and-Place & Box Build
Product family: Industrial IoT Controller Boards.
Flow: EMS Silicon & PCB Distributors → Solder Paste Print & SPI → SMD Pick & Place → Reflow Oven & 3D AOI → Selective Wave Soldering → ICT & Box-Build Pack → Industrial OEM Clients
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Solder Paste Print & SPI | 12.6 s | 25 min | 95% | 98.6% | 1,920 | 2,880 (1.20 d) | 3,875 |
| 2. SMD Pick & Place | 18.4 s | 35 min | 91% | 97.4% | 1,920 | 3,360 (1.40 d) | 2,475 |
| 3. Reflow Oven & 3D AOI | 24.1 s | 45 min | 84% | 95.4% | 2,400 | 4,320 (1.80 d) | 1,706 |
| 4. Selective Wave Soldering | 17.6 s | 18 min | 93% | 98.1% | 960 | 2,400 (1.00 d) | 2,659 |
| 5. ICT & Box-Build Pack | 15.3 s | 15 min | 95% | 98.8% | 600 | 1,920 (0.80 d) | 3,092 |
Key figures
- Takt time
- 22.5 s
- Lead time
- 7.40 d
- Value-added time
- 88.0 s
- Process cycle efficiency (PCE)
- 0.022%
- Rolled throughput yield (RTY)
- 88.8%
- Customer demand per day
- 2,400 boards
- Line capacity per day
- 1,706 boards
- Bottleneck
- Reflow Oven & 3D AOI
Reading the bottleneck
The bottleneck is "Reflow Oven & 3D AOI": it can process 1,706 boards per day against a demand of 2,400 boards, so it falls short of demand by 28.9%. Once downtime and scrap are counted, its cycle time grows from 24.1 s to 30.1 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 4.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of PCB SMT & Box-Build EMS: PCB SMT & Box-Build EMS
- Automotive ASIL-D EV BMS Mainboard SMT
- 64T64R 5G Massive-MIMO Antenna PCB Line
- 77GHz Automotive ADAS Radar Sensor PCB
- ISO-13485 Medical Ultrasound Beamformer PCB
- Dual-Socket AI GPU Server Motherboard
- NB-IoT Ultrasonic Smart Water/Gas Meter
- Three-Phase Industrial VFD Inverter Gate Board
- Modular DIN-Rail Industrial Safety PLC I/O
- PCI-PTS Secure EMV Payment Terminal PCBA
- Matter & Thread Smart Home Gateway Line
- Rigid-Flex Polyimide Satellite Bus Board