Takt Time Calculator
Takt time is the pace at which you must produce to meet customer demand: the available production time divided by the demand. If a step takes longer than the takt time to produce one unit, it cannot keep up with the customer.
Free to use, no account. The calculation uses the same functions as the editor, so both always give the same figures.
Inputs
Formula and units
- Net available time (s/day) = shifts × (hours per shift × 60 − break minutes) × 60
- Takt time (s/unit) = net available time (s/day) ÷ customer demand (units/day)
Units: seconds per unit. Breaks are deducted from each shift.
Worked example
Example values
- Customer demand (units per day)
- 1,200
- Shifts per day
- 2
- Hours per shift
- 8
- Breaks per shift (minutes)
- 30
Result
- Net available time per day
- 900 min
- Takt time
- 45.0 s
With these inputs the takt time is 45.0 s: one unit must leave the line at that pace.
Go further
- See the takt time of a complete bottling line: 18,000 bph PET Bottling Line
- Open the free editor