18,000 bph PET Bottling Line
Product family: PET 1.5L Carbonated Packs.
Flow: PET Preform Supplier → PET Blow Molding → Filling & Capping → Labeling & Coding → Shrink Wrapping → Palletizing & Stretch → National Retail Distribution
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. PET Blow Molding | 5.7 s | 45 min | 92% | 98.8% | 11,520 | 17,280 (1.80 d) | 12,558 |
| 2. Filling & Capping | 8.8 s | 65 min | 84% | 96.8% | 11,520 | 14,400 (1.50 d) | 7,184 |
| 3. Labeling & Coding | 6.4 s | 25 min | 92% | 98.2% | 5,760 | 13,440 (1.40 d) | 11,081 |
| 4. Shrink Wrapping | 6.8 s | 30 min | 91% | 98.5% | 4,800 | 11,520 (1.20 d) | 10,203 |
| 5. Palletizing & Stretch | 5.4 s | 10 min | 96% | 99.5% | 2,880 | 7,680 (0.80 d) | 13,974 |
Key figures
- Takt time
- 8.4 s
- Lead time
- 8.20 d
- Value-added time
- 33.1 s
- Process cycle efficiency (PCE)
- 0.005%
- Rolled throughput yield (RTY)
- 92.0%
- Customer demand per day
- 9,600 packs
- Line capacity per day
- 7,184 packs
- Bottleneck
- Filling & Capping
Reading the bottleneck
The bottleneck is "Filling & Capping": it can process 7,184 packs per day against a demand of 9,600 packs, so it falls short of demand by 25.2%. Once downtime and scrap are counted, its cycle time grows from 8.8 s to 10.8 s, against a takt of 8.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 1.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Bottling, Canning & Beverages: Bottling, Canning & Beverages
- 45,000 cph Aluminum Craft Beer Canning Line
- 30,000 bph Returnable Glass Soda Line
- 8,000 bph 5L Spring Water PET Combi-Line
- High-Pressure Pasteurized (HPP) Cold Juice
- Hot-Fill / Aseptic Sport Isotonic Cap Line
- 60mL Functional Energy & Vitamin Shot Line
- Organic Glass Kombucha Secondary Ferment
- Retort Nitro Cold-Brew Aluminum Can Line
- 12,000 bph Winery Bottling, Cork & Capsule
- Automated Stainless 30L Beer Keg Wash & Fill
- High-Value Distilled Spirits Tax-Stamp Line