How to Map a Value Stream
Published by VSME.net
A current-state value stream map shows how one product family flows from supplier to customer, what each step takes, and where material waits. It is a few hours of observation, not a software exercise: the map is only as good as the numbers you measure on the floor.
Scope
Map one product family, not the whole plant. A family is a group of products that go through the same steps and the same equipment, for example all the drinks that run on one filling line. Decide where the map starts and ends: usually the supplier delivery at one end and the shipment to the customer at the other.
Before you walk the process, write down the customer demand per day and the available production time per day (shifts multiplied by working hours, minus breaks). These two figures give the takt time, the pace the customer asks for, and every later judgement refers to it.
Worked steps
- Customer and demand. Measure units per day over a representative period, the shipping frequency and the packaging unit. Takt time is the available time divided by the demand.
- Walk the flow, from the customer back to the supplier. Walking against the flow shows first what pulls the process. Note every step where the product is worked on or stops.
- Time each step. Measure the cycle time per unit (several observations with a stopwatch), the changeover time, the uptime, the first-pass yield, the batch size and the number of operators. Use observed values, not the standards stored in the system.
- Count the stock. Measure the units waiting before each step and in finished goods, then divide by the daily demand to express each stock in days. That is the waiting time.
- Draw the information flow. Note how each step learns what to produce: forecast, planning run, schedule or kanban signal. Mark as push the steps that send product on without a downstream request.
- Compute the indicators. Lead time is the waiting time plus the processing time. Value-added time is the sum of the cycle times. Process cycle efficiency (PCE) is the value-added time divided by the lead time. The bottleneck is the step with the lowest daily capacity once downtime, scrap and changeovers are counted.
Worked example
The catalog template "18,000 bph PET Bottling Line" applies these steps. Customer demand is 9,600 packs per day on 3 shifts, which gives a takt time of 8.4 s. The line has 5 steps: PET Blow Molding, Filling & Capping, Labeling & Coding, Shrink Wrapping, Palletizing & Stretch.
The cycle times add up to 33.1 s of value-added time, while a unit spends 8.20 d in the process, so the PCE is 0.005%. The bottleneck is "Filling & Capping": it can process 7,184 packs per day. These figures are illustrative starting values, not benchmarks: replace them with your own measurements.
Check the result
Read the map in this order. First compare the capacity of each step with the demand: a step below the demand limits the whole line. Then look at the largest stocks. Waiting time is usually far larger than processing time, which is why PCE is low and why the first gains often come from stock, batch size and scheduling rather than from faster machines. Finally look at changeovers and yield on the bottleneck, because time lost there is lost for the whole line.
Then check the map before you use it. Do the bottleneck cycle time and the daily demand agree with what the plant really ships? Does the lead time match the time a tagged order takes from receipt to shipment? Ask the operators to correct what you drew.
Common mistakes
- Mapping several product families on one map, so that no step has a clear demand.
- Using standard times from the ERP instead of observed times, which hides downtime and rework.
- Comparing a step with the takt time without counting changeovers and scrap.
- Drawing the flow from a description instead of walking it.
- Measuring the stock on a single day instead of over a representative period.
- Treating the illustrative figures of a template as a benchmark for your own plant.