Multi-Brand Ghost Kitchen Delivery Aggregator
Product family: 5-Brand Virtual Restaurant Pod.
Flow: Central Prep Sous-Vide Hub → Tablet Aggregator Auto-Ingest → Multi-Brand Pod Cook & Sear → Tamper Sticker & Thermal Bag → Rider Lockers Warm Holding → Dispatch SLA Timer Verification → Third-Party Delivery App Riders
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Tablet Aggregator Auto-Ingest | 56.0 s | 10 min | 95% | 98.6% | 310 | 868 (1.40 d) | 883 |
| 2. Multi-Brand Pod Cook & Sear | 70.0 s | 8 min | 93% | 97.5% | 248 | 1,054 (1.70 d) | 684 |
| 3. Tamper Sticker & Thermal Bag | 93.0 s | 12 min | 88% | 94.0% | 124 | 744 (1.20 d) | 448 |
| 4. Rider Lockers Warm Holding | 61.0 s | 5 min | 96% | 98.8% | 62 | 372 (0.60 d) | 793 |
| 5. Dispatch SLA Timer Verification | 45.0 s | 3 min | 98% | 99.4% | 62 | 248 (0.40 d) | 1,130 |
Key figures
- Takt time
- 87.1 s
- Lead time
- 6.01 d
- Value-added time
- 325 s
- Process cycle efficiency (PCE)
- 0.10%
- Rolled throughput yield (RTY)
- 88.7%
- Customer demand per day
- 620 orders
- Line capacity per day
- 448 orders
- Bottleneck
- Tamper Sticker & Thermal Bag
Reading the bottleneck
The bottleneck is "Tamper Sticker & Thermal Bag": it can process 448 orders per day against a demand of 620 orders, so it falls short of demand by 27.7%. Once downtime and scrap are counted, its cycle time grows from 93.0 s to 112 s, against a takt of 87.1 s. The largest loss at this step is equipment downtime (uptime 88%), about 12.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Retail Stores, Omnichannel & QSR: Retail Stores, Omnichannel & QSR
- Store Replenishment & Click-and-Collect
- Hypermarket Dawn Fresh Produce Mist & Display
- Community Pharmacy Rx Dispense & OTC Shelf
- Quick-Service Burger Kitchen Peak-Hour Make Line
- High-Volume Urban Coffee & Morning Pastry Pull
- Retail Optical 1-Hour Single-Vision Lens Lab
- DIY Home Center Drive-Thru Timber & Pallet Bay
- Luxury Fashion Boutique Clienteling & Tailoring
- Self-Checkout & Smart-Cart Frictionless Exit
- High-Security Consumer Tech Cage-to-Counter
- Bookstore Curbside Pickup & Local Author Print