Dual-System Vocational Apprenticeship Certification

Product family: Industry-Chamber Skills Sign.

Flow: Host Plants & Trade Schools → Employer Contract Registration → Mid-Term Practical Shop Audit → Capstone Jury Project Eval → Chamber Written Exam Grade → Master Craft Credential Print → Certified Technicians

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Dual-System Vocational Apprenticeship CertificationSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Host Plants & Trade Schools → Employer Contract Registration (182 s) → Mid-Term Practical Shop Audit (216 s) → Capstone Jury Project Eval (307 s) → Chamber Written Exam Grade (199 s) → Master Craft Credential Print (136 s) → Certified Technicians.SUPPLIERHost Plants &Trade SchoolsI1.40 d1Employer ContractRegistrationC/T 182 sI1.80 d2Mid-TermPractical Shop…C/T 216 sI3.80 d3Capstone JuryProject EvalC/T 307 sI0.91 d4Chamber WrittenExam GradeC/T 199 sI0.40 d5Master CraftCredential PrintC/T 136 sI0.40 dCUSTOMERCertifiedTechnicians95 / files

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Employer Contract Registration182 s5 min96%91.5%24133 (1.40 d)125
2. Mid-Term Practical Shop Audit216 s8 min94%93.8%24171 (1.80 d)102
3. Capstone Jury Project Eval307 s15 min85%88.5%19361 (3.80 d)55
4. Chamber Written Exam Grade199 s5 min96%97.6%1486 (0.91 d)118
5. Master Craft Credential Print136 s2 min99%99.4%1038 (0.40 d)187

Key figures

Takt time
284 s
Lead time
8.74 d
Value-added time
1,040 s
Process cycle efficiency (PCE)
0.44%
Rolled throughput yield (RTY)
73.7%
Customer demand per day
95 files
Line capacity per day
55 files
Bottleneck
Capstone Jury Project Eval

Reading the bottleneck

The bottleneck is "Capstone Jury Project Eval": it can process 55 files per day against a demand of 95 files, so it falls short of demand by 42.0%. Once downtime and scrap are counted, its cycle time grows from 307 s to 408 s, against a takt of 284 s. The largest loss at this step is equipment downtime (uptime 85%), about 54.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.