Data Center 2MW Diesel Gen & UPS Load-Bank Test
Product family: Tier-IV Integrated IST Test.
Flow: Portable Resistive Load Banks → Load-Bank Cable Hookup & Lock → 0–100% Step Load Transient Run → UPS Failover Black-Start Cycle → IR Thermography Busbar Check → Cx Level-4 Commissioning Cert → Data Center Commissioning
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Load-Bank Cable Hookup & Lock | 2,970 s | 15 min | 95% | 98.5% | 3 | 8 (1.33 d) | 8 |
| 2. 0–100% Step Load Transient Run | 3,690 s | 20 min | 92% | 97.6% | 2 | 10 (1.67 d) | 6 |
| 3. UPS Failover Black-Start Cycle | 4,815 s | 25 min | 85% | 94.8% | 3 | 13 (2.17 d) | 4 |
| 4. IR Thermography Busbar Check | 3,330 s | 10 min | 95% | 98.2% | 2 | 5 (0.83 d) | 7 |
| 5. Cx Level-4 Commissioning Cert | 2,520 s | 8 min | 97% | 99.4% | 1 | 4 (0.67 d) | 10 |
Key figures
- Takt time
- 4,500 s
- Lead time
- 7.98 d
- Value-added time
- 17,325 s
- Process cycle efficiency (PCE)
- 8.0%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 6 cases
- Line capacity per day
- 4 cases
- Bottleneck
- UPS Failover Black-Start Cycle
Reading the bottleneck
The bottleneck is "UPS Failover Black-Start Cycle": it can process 4 cases per day against a demand of 6 cases, so it falls short of demand by 33.1%. Once downtime and scrap are counted, its cycle time grows from 4,815 s to 5,975 s, against a takt of 4,500 s. The largest loss at this step is equipment downtime (uptime 85%), about 850 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Cloud Data Centers & Hyperscale Infra: Cloud Data Centers & Hyperscale Infra
- Factory L11 Pre-Integrated Liquid AI Server Rack
- Data Center Direct-to-Chip CDU Cooling Loop
- 1024-GPU InfiniBand NDR Fat-Tree Cluster Cable
- Automated Bare-Metal Dedicated Server Provision
- Enterprise Private Colocation Cage Handover
- Modular Edge Micro-Datacenter Outdoor Container
- Automated Immutable Air-Gap Backup Restore Test
- Enterprise Internal PKI & TLS Certificate Rotation
- Continuous SOC2 Type-II Automated Evidence Pack
- New Cloud Availability Zone Core Fleet Stand-Up
- Data Center High-Rate VRLA / Lithium String Swap