Build-to-Rent Apartment Move-Out Make-Ready

Product family: 5-Day Unit Re-Lease Turn.

Flow: Paint, Carpet & Appliance → Move-Out Deposit & Scope Walk → Appliance & Plumbing Service → Full Repaint & Steam Clean → Quality Final Ready Check → Digital Tour Listing Live → Leasing Operations

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Build-to-Rent Apartment Move-Out Make-ReadySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Paint, Carpet & Appliance → Move-Out Deposit & Scope Walk (478 s) → Appliance & Plumbing Service (825 s) → Full Repaint & Steam Clean (648 s) → Quality Final Ready Check (540 s) → Digital Tour Listing Live (370 s) → Leasing Operations.SUPPLIERPaint, Carpet &ApplianceI1.51 d1Move-Out Deposit& Scope WalkC/T 478 sI3.20 d2Appliance &Plumbing ServiceC/T 825 sI1.80 d3Full Repaint &Steam CleanC/T 648 sI0.91 d4Quality FinalReady CheckC/T 540 sI0.40 d5Digital TourListing LiveC/T 370 sI0.40 dCUSTOMERLeasingOperations35 / rooms

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Move-Out Deposit & Scope Walk478 s10 min97%91.5%1153 (1.51 d)47
2. Appliance & Plumbing Service825 s15 min86%88.5%9112 (3.20 d)22
3. Full Repaint & Steam Clean648 s15 min91%95.8%763 (1.80 d)30
4. Quality Final Ready Check540 s8 min95%97.8%532 (0.91 d)41
5. Digital Tour Listing Live370 s5 min98%99.1%414 (0.40 d)64

Key figures

Takt time
771 s
Lead time
8.33 d
Value-added time
2,861 s
Process cycle efficiency (PCE)
1.3%
Rolled throughput yield (RTY)
75.2%
Customer demand per day
35 rooms
Line capacity per day
22 rooms
Bottleneck
Appliance & Plumbing Service

Reading the bottleneck

The bottleneck is "Appliance & Plumbing Service": it can process 22 rooms per day against a demand of 35 rooms, so it falls short of demand by 38.1%. Once downtime and scrap are counted, its cycle time grows from 825 s to 1,084 s, against a takt of 771 s. The largest loss at this step is equipment downtime (uptime 86%), about 134 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.