400-Case/Hr Optical Shell Egg Wash & Pack
Product family: UV-Sanitized Pulp 12-Egg Cartons.
Flow: Free-Range Contract Farms → Warm Sanitize Wash & UV-C → Acoustic Crack & Blood Detect → Precision Weight Scale Lane Drop → Molded Pulp Lid Stamp & Ink → Cooler +12°C Cross-Dock → Supermarket Morning Pull
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Warm Sanitize Wash & UV-C | 1.2 s | 15 min | 95% | 97.6% | 12,600 | 25,200 (0.60 d) | 39,406 |
| 2. Acoustic Crack & Blood Detect | 1.2 s | 20 min | 92% | 98.2% | 16,800 | 29,400 (0.70 d) | 38,396 |
| 3. Precision Weight Scale Lane Drop | 1.4 s | 30 min | 84% | 96.4% | 21,000 | 37,800 (0.90 d) | 29,151 |
| 4. Molded Pulp Lid Stamp & Ink | 1.2 s | 10 min | 95% | 98.8% | 8,400 | 16,800 (0.40 d) | 39,891 |
| 5. Cooler +12°C Cross-Dock | 1.2 s | 8 min | 97% | 99.4% | 8,400 | 16,800 (0.40 d) | 41,460 |
Key figures
- Takt time
- 1.3 s
- Lead time
- 3.50 d
- Value-added time
- 6.2 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 42,000 packs
- Line capacity per day
- 29,151 packs
- Bottleneck
- Precision Weight Scale Lane Drop
Reading the bottleneck
The bottleneck is "Precision Weight Scale Lane Drop": it can process 29,151 packs per day against a demand of 42,000 packs, so it falls short of demand by 30.6%. Once downtime and scrap are counted, its cycle time grows from 1.4 s to 1.7 s, against a takt of 1.3 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Meat, Poultry & Seafood Processing: Meat, Poultry & Seafood Processing
- 400g Skinless Poultry Breast MAP Tray Line
- Norwegian Salmon Fillet Vacuum Skin Pack (VSP)
- 80/20 Frozen Beef Burger Patty IQF Tunnel
- 18-Month Dry-Cured Ham High-Speed Slicing
- Peeled & Deveined Frozen Shrimp Glaze Line
- High-Moisture Twin-Screw Plant Protein Burger
- Slow-Cooked Sous-Vide Chef Sauce & Protein
- Continuous Beechwood Smoke Frankfurter Line
- Steamed Skipjack Tuna Retort Olive-Oil Can
- Continuous Sheeted Alaska Pollock Surimi Crab
- Fresh Triple-Wash Chilled Deli Pasta Salad