Fresh Triple-Wash Chilled Deli Pasta Salad
Product family: 300g Tamper-Evident Bowls.
Flow: Blanched Pasta & Fresh Veg → Ozone Ice-Water Veg Wash → Chilled Blend & Volumetric Fill → Foil Heat-Seal Film Membrane → Snap Clear Lid & Weight Check → +2°C Crate & Same-Night Drop → ConvenienceGrab & Go
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Ozone Ice-Water Veg Wash | 2.5 s | 15 min | 95% | 97.6% | 4,500 | 9,000 (0.60 d) | 18,915 |
| 2. Chilled Blend & Volumetric Fill | 3.0 s | 20 min | 92% | 98.2% | 6,000 | 10,500 (0.70 d) | 15,358 |
| 3. Foil Heat-Seal Film Membrane | 3.9 s | 30 min | 84% | 96.4% | 7,500 | 13,500 (0.90 d) | 10,465 |
| 4. Snap Clear Lid & Weight Check | 2.5 s | 10 min | 95% | 98.8% | 3,000 | 6,000 (0.40 d) | 19,147 |
| 5. +2°C Crate & Same-Night Drop | 2.0 s | 8 min | 97% | 99.4% | 3,000 | 6,000 (0.40 d) | 24,876 |
Key figures
- Takt time
- 3.6 s
- Lead time
- 3.50 d
- Value-added time
- 13.9 s
- Process cycle efficiency (PCE)
- 0.007%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 15,000 packs
- Line capacity per day
- 10,465 packs
- Bottleneck
- Foil Heat-Seal Film Membrane
Reading the bottleneck
The bottleneck is "Foil Heat-Seal Film Membrane": it can process 10,465 packs per day against a demand of 15,000 packs, so it falls short of demand by 30.2%. Once downtime and scrap are counted, its cycle time grows from 3.9 s to 4.8 s, against a takt of 3.6 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Meat, Poultry & Seafood Processing: Meat, Poultry & Seafood Processing
- 400g Skinless Poultry Breast MAP Tray Line
- Norwegian Salmon Fillet Vacuum Skin Pack (VSP)
- 80/20 Frozen Beef Burger Patty IQF Tunnel
- 18-Month Dry-Cured Ham High-Speed Slicing
- Peeled & Deveined Frozen Shrimp Glaze Line
- High-Moisture Twin-Screw Plant Protein Burger
- Slow-Cooked Sous-Vide Chef Sauce & Protein
- Continuous Beechwood Smoke Frankfurter Line
- 400-Case/Hr Optical Shell Egg Wash & Pack
- Steamed Skipjack Tuna Retort Olive-Oil Can
- Continuous Sheeted Alaska Pollock Surimi Crab