High-Moisture Twin-Screw Plant Protein Burger
Product family: Soy/Pea Textured Vegan Patties.
Flow: Pea Isolate & Beet Supplier → High-Moisture Twin Extrude → Cold Hydration & Fat Emulsify → Forming Drum & Steam Grill Mark → Fluid-Bed IQF Blast Freeze → MAP Retail Tray & Checkweigh → Plant-Based Retail Aisles
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. High-Moisture Twin Extrude | 2.1 s | 15 min | 95% | 97.6% | 5,400 | 10,800 (0.60 d) | 22,518 |
| 2. Cold Hydration & Fat Emulsify | 2.5 s | 20 min | 92% | 98.2% | 7,200 | 12,600 (0.70 d) | 18,430 |
| 3. Forming Drum & Steam Grill Mark | 3.2 s | 30 min | 84% | 96.4% | 9,000 | 16,200 (0.90 d) | 12,754 |
| 4. Fluid-Bed IQF Blast Freeze | 2.1 s | 10 min | 95% | 98.8% | 3,600 | 7,200 (0.40 d) | 22,795 |
| 5. MAP Retail Tray & Checkweigh | 1.7 s | 8 min | 97% | 99.4% | 3,600 | 7,200 (0.40 d) | 29,266 |
Key figures
- Takt time
- 3.0 s
- Lead time
- 3.50 d
- Value-added time
- 11.6 s
- Process cycle efficiency (PCE)
- 0.006%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 18,000 packs
- Line capacity per day
- 12,754 packs
- Bottleneck
- Forming Drum & Steam Grill Mark
Reading the bottleneck
The bottleneck is "Forming Drum & Steam Grill Mark": it can process 12,754 packs per day against a demand of 18,000 packs, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 3.2 s to 4.0 s, against a takt of 3.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Meat, Poultry & Seafood Processing: Meat, Poultry & Seafood Processing
- 400g Skinless Poultry Breast MAP Tray Line
- Norwegian Salmon Fillet Vacuum Skin Pack (VSP)
- 80/20 Frozen Beef Burger Patty IQF Tunnel
- 18-Month Dry-Cured Ham High-Speed Slicing
- Peeled & Deveined Frozen Shrimp Glaze Line
- Slow-Cooked Sous-Vide Chef Sauce & Protein
- Continuous Beechwood Smoke Frankfurter Line
- 400-Case/Hr Optical Shell Egg Wash & Pack
- Steamed Skipjack Tuna Retort Olive-Oil Can
- Continuous Sheeted Alaska Pollock Surimi Crab
- Fresh Triple-Wash Chilled Deli Pasta Salad