Steamed Skipjack Tuna Retort Olive-Oil Can
Product family: 3-Pack 80g Easy-Open Cans.
Flow: Purse Seine Cold Vessels → Water Defrost & Steam Precook → Optical Bone & Dark-Meat Clean → High-Speed Chunk Pack & Oil → Steam Vacuum Double Seamer → Rotary Overpressure Retort → Mediterranean & Global Retail
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Water Defrost & Steam Precook | 1.2 s | 15 min | 95% | 97.6% | 14,400 | 28,800 (0.60 d) | 60,268 |
| 2. Optical Bone & Dark-Meat Clean | 1.4 s | 20 min | 92% | 98.2% | 19,200 | 33,600 (0.70 d) | 50,335 |
| 3. High-Speed Chunk Pack & Oil | 1.8 s | 30 min | 84% | 96.4% | 24,000 | 43,200 (0.90 d) | 34,820 |
| 4. Steam Vacuum Double Seamer | 1.2 s | 10 min | 95% | 98.8% | 9,600 | 19,200 (0.40 d) | 61,009 |
| 5. Rotary Overpressure Retort | 1.2 s | 8 min | 97% | 99.4% | 9,600 | 19,200 (0.40 d) | 63,154 |
Key figures
- Takt time
- 1.7 s
- Lead time
- 3.50 d
- Value-added time
- 6.8 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 48,000 packs
- Line capacity per day
- 34,820 packs
- Bottleneck
- High-Speed Chunk Pack & Oil
Reading the bottleneck
The bottleneck is "High-Speed Chunk Pack & Oil": it can process 34,820 packs per day against a demand of 48,000 packs, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 1.8 s to 2.2 s, against a takt of 1.7 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Meat, Poultry & Seafood Processing: Meat, Poultry & Seafood Processing
- 400g Skinless Poultry Breast MAP Tray Line
- Norwegian Salmon Fillet Vacuum Skin Pack (VSP)
- 80/20 Frozen Beef Burger Patty IQF Tunnel
- 18-Month Dry-Cured Ham High-Speed Slicing
- Peeled & Deveined Frozen Shrimp Glaze Line
- High-Moisture Twin-Screw Plant Protein Burger
- Slow-Cooked Sous-Vide Chef Sauce & Protein
- Continuous Beechwood Smoke Frankfurter Line
- 400-Case/Hr Optical Shell Egg Wash & Pack
- Continuous Sheeted Alaska Pollock Surimi Crab
- Fresh Triple-Wash Chilled Deli Pasta Salad