Continuous Beechwood Smoke Frankfurter Line
Product family: Peeled Skinless Cooked Sausages.
Flow: Lean Pork/Poultry & Spices → Bowl Chopper Emulsion Vacuum → High-Speed Stuffer & Linker → Continuous Smoke-Steam-Chill → High-Speed Steam Peeler → Vacuum 8-Pack & Case Sort → Grocery & Stadiums
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Bowl Chopper Emulsion Vacuum | 1.7 s | 15 min | 95% | 97.6% | 10,200 | 20,400 (0.60 d) | 42,542 |
| 2. High-Speed Stuffer & Linker | 2.0 s | 20 min | 92% | 98.2% | 13,600 | 23,800 (0.70 d) | 35,234 |
| 3. Continuous Smoke-Steam-Chill | 2.5 s | 30 min | 84% | 96.4% | 17,000 | 30,600 (0.90 d) | 25,070 |
| 4. High-Speed Steam Peeler | 1.7 s | 10 min | 95% | 98.8% | 6,800 | 13,600 (0.40 d) | 43,065 |
| 5. Vacuum 8-Pack & Case Sort | 1.3 s | 8 min | 97% | 99.4% | 6,800 | 13,600 (0.40 d) | 58,296 |
Key figures
- Takt time
- 2.4 s
- Lead time
- 3.50 d
- Value-added time
- 9.2 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 34,000 packs
- Line capacity per day
- 25,070 packs
- Bottleneck
- Continuous Smoke-Steam-Chill
Reading the bottleneck
The bottleneck is "Continuous Smoke-Steam-Chill": it can process 25,070 packs per day against a demand of 34,000 packs, so it falls short of demand by 26.3%. Once downtime and scrap are counted, its cycle time grows from 2.5 s to 3.1 s, against a takt of 2.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Meat, Poultry & Seafood Processing: Meat, Poultry & Seafood Processing
- 400g Skinless Poultry Breast MAP Tray Line
- Norwegian Salmon Fillet Vacuum Skin Pack (VSP)
- 80/20 Frozen Beef Burger Patty IQF Tunnel
- 18-Month Dry-Cured Ham High-Speed Slicing
- Peeled & Deveined Frozen Shrimp Glaze Line
- High-Moisture Twin-Screw Plant Protein Burger
- Slow-Cooked Sous-Vide Chef Sauce & Protein
- 400-Case/Hr Optical Shell Egg Wash & Pack
- Steamed Skipjack Tuna Retort Olive-Oil Can
- Continuous Sheeted Alaska Pollock Surimi Crab
- Fresh Triple-Wash Chilled Deli Pasta Salad