Cold-Extracted Extra Virgin Olive Oil Bottle Line
Product family: 750mL Dark Glass EVOO.
Flow: Estate Olive Centrifuges → Peroxide & Acidity Tank Test → N2 Inerting Polish Micro-Filter → Gravity UV-Glass Fill & Pourer → Wrap-Around Foil Label → Case Drop Pack & Export → Specialty & Supermarket
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Peroxide & Acidity Tank Test | 2.5 s | 25 min | 95% | 99.1% | 21,000 | 25,200 (1.80 d) | 19,959 |
| 2. N2 Inerting Polish Micro-Filter | 3.2 s | 45 min | 91% | 98.2% | 16,800 | 22,400 (1.60 d) | 14,452 |
| 3. Gravity UV-Glass Fill & Pourer | 4.1 s | 50 min | 84% | 96.5% | 14,000 | 23,800 (1.70 d) | 10,083 |
| 4. Wrap-Around Foil Label | 2.8 s | 10 min | 95% | 98.8% | 7,000 | 15,400 (1.10 d) | 17,699 |
| 5. Case Drop Pack & Export | 2.2 s | 10 min | 97% | 99.5% | 5,600 | 14,000 (1.00 d) | 23,032 |
Key figures
- Takt time
- 3.9 s
- Lead time
- 9.20 d
- Value-added time
- 14.8 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 92.3%
- Customer demand per day
- 14,000 packs
- Line capacity per day
- 10,083 packs
- Bottleneck
- Gravity UV-Glass Fill & Pourer
Reading the bottleneck
The bottleneck is "Gravity UV-Glass Fill & Pourer": it can process 10,083 packs per day against a demand of 14,000 packs, so it falls short of demand by 28.0%. Once downtime and scrap are counted, its cycle time grows from 4.1 s to 5.1 s, against a takt of 3.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.8 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Edible Oils, Milling, Coffee & Dry Goods: Edible Oils, Milling, Coffee & Dry Goods
- 400-Ton/Day Pneumatic Wheat Flour Mill
- Bronze-Die High-Temp Durum Spaghetti Line
- Fluid-Bed Coffee Roasting & N2 Valve Bag Line
- Hot-Break 36° Brix Aseptic Tomato Paste Drum
- Continuous Wash-Slice-Fry Potato Chip Bag Line
- Inline Colloid Mill Emulsion Mayo Glass Jar Line
- Steam-Parboiled & Optical Color-Sorted Rice Line
- Vacuum Pan Refined White Beet Sugar Pack Line
- Hulled Stone-Milled Roasted Sesame Tahini Line
- Steamed Rolled Durum Couscous Continuous Dryer
- Physically Refined Sunflower 5L PET Bottle Line