Hulled Stone-Milled Roasted Sesame Tahini Line

Product family: 500g Pet Jar & 18kg Pail.

Flow: Roasted Sesame Silos → Optical Hulled Seed Roast → Granite Two-Stage Stone Mill → Shell-Tube Paste Cool & Store → Servo Volumetric Fill & Foil Seal → Metal Check & Export Box → Middle East & EU Retail

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Hulled Stone-Milled Roasted Sesame Tahini LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Roasted Sesame Silos → Optical Hulled Seed Roast (3.6 s) → Granite Two-Stage Stone Mill (4.8 s) → Shell-Tube Paste Cool & Store (6.1 s) → Servo Volumetric Fill & Foil Seal (4.1 s) → Metal Check & Export Box (3.2 s) → Middle East & EU Retail.SUPPLIERRoasted SesameSilosI1.80 d1Optical HulledSeed RoastC/T 3.6 sI1.60 d2Granite Two-StageStone MillC/T 4.8 sI1.70 d3Shell-Tube PasteCool & StoreC/T 6.1 sI1.10 d4Servo VolumetricFill & Foil SealC/T 4.1 sI1.00 d5Metal Check &Export BoxC/T 3.2 sI2.00 dCUSTOMERMiddle East &EU Retail9,500 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Optical Hulled Seed Roast3.6 s25 min95%99.1%14,25017,100 (1.80 d)13,860
2. Granite Two-Stage Stone Mill4.8 s45 min91%98.2%11,40015,200 (1.60 d)9,634
3. Shell-Tube Paste Cool & Store6.1 s50 min84%96.5%9,50016,150 (1.70 d)6,777
4. Servo Volumetric Fill & Foil Seal4.1 s10 min95%98.8%4,75010,450 (1.10 d)12,087
5. Metal Check & Export Box3.2 s10 min97%99.5%3,8009,500 (1.00 d)15,834

Key figures

Takt time
5.7 s
Lead time
9.20 d
Value-added time
21.8 s
Process cycle efficiency (PCE)
0.004%
Rolled throughput yield (RTY)
92.3%
Customer demand per day
9,500 packs
Line capacity per day
6,777 packs
Bottleneck
Shell-Tube Paste Cool & Store

Reading the bottleneck

The bottleneck is "Shell-Tube Paste Cool & Store": it can process 6,777 packs per day against a demand of 9,500 packs, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 6.1 s to 7.5 s, against a takt of 5.7 s. The largest loss at this step is equipment downtime (uptime 84%), about 1.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Edible Oils, Milling, Coffee & Dry Goods: Edible Oils, Milling, Coffee & Dry Goods