Hot-Break 36° Brix Aseptic Tomato Paste Drum

Product family: 220kg Sterile Steel Drums.

Flow: Field Tomato Harvesters → Hydro-Flume & Optical Sort → Hot-Break Enzyme Inactivate → 4-Effect Vacuum Evaporator → Tubular UHT & Aseptic Drum Fill → Brix/Howard Mold Lab Release → Sauce & Ketchup Processors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Hot-Break 36° Brix Aseptic Tomato Paste DrumSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Field Tomato Harvesters → Hydro-Flume & Optical Sort (61.0 s) → Hot-Break Enzyme Inactivate (80.0 s) → 4-Effect Vacuum Evaporator (102 s) → Tubular UHT & Aseptic Drum Fill (69.0 s) → Brix/Howard Mold Lab Release (53.0 s) → Sauce & Ketchup Processors.SUPPLIERField TomatoHarvestersI1.80 d1Hydro-Flume &Optical SortC/T 61.0 sI1.60 d2Hot-Break EnzymeInactivateC/T 80.0 sI1.70 d34-Effect VacuumEvaporatorC/T 102 sI1.10 d4Tubular UHT &Aseptic Drum FillC/T 69.0 sI1.00 d5Brix/Howard MoldLab ReleaseC/T 53.0 sI2.00 dCUSTOMERSauce & KetchupProcessors850 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Hydro-Flume & Optical Sort61.0 s25 min95%99.1%1,2751,530 (1.80 d)1,235
2. Hot-Break Enzyme Inactivate80.0 s45 min91%98.2%1,0201,360 (1.60 d)880
3. 4-Effect Vacuum Evaporator102 s50 min84%96.5%8501,445 (1.70 d)620
4. Tubular UHT & Aseptic Drum Fill69.0 s10 min95%98.8%425935 (1.10 d)1,086
5. Brix/Howard Mold Lab Release53.0 s10 min97%99.5%340850 (1.00 d)1,448

Key figures

Takt time
95.3 s
Lead time
9.20 d
Value-added time
365 s
Process cycle efficiency (PCE)
0.049%
Rolled throughput yield (RTY)
92.3%
Customer demand per day
850 batches
Line capacity per day
620 batches
Bottleneck
4-Effect Vacuum Evaporator

Reading the bottleneck

The bottleneck is "4-Effect Vacuum Evaporator": it can process 620 batches per day against a demand of 850 batches, so it falls short of demand by 27.1%. Once downtime and scrap are counted, its cycle time grows from 102 s to 126 s, against a takt of 95.3 s. The largest loss at this step is equipment downtime (uptime 84%), about 19.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.