Thermostable Taq Polymerase Enzyme Ferment
Product family: Ultra-Pure Molecular Reagents.
Flow: Biotech Fermentation Salts → Fed-Batch 500L Expression → Heat-Shock Clarify & Spin → Heparin-Affinity Elution → Glycerol Buffer Formulate → DNase/RNase Contamination QC → PCR Kit Manufacturers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Fed-Batch 500L Expression | 518 s | 30 min | 95% | 98.4% | 75 | 120 (1.60 d) | 94 |
| 2. Heat-Shock Clarify & Spin | 619 s | 40 min | 91% | 97.2% | 113 | 135 (1.80 d) | 75 |
| 3. Heparin-Affinity Elution | 778 s | 60 min | 84% | 94.5% | 75 | 180 (2.40 d) | 51 |
| 4. Glycerol Buffer Formulate | 562 s | 25 min | 93% | 98.1% | 38 | 90 (1.20 d) | 83 |
| 5. DNase/RNase Contamination QC | 475 s | 15 min | 95% | 97.8% | 60 | 113 (1.51 d) | 103 |
Key figures
- Takt time
- 720 s
- Lead time
- 10.1 d
- Value-added time
- 2,952 s
- Process cycle efficiency (PCE)
- 0.54%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 75 batches
- Line capacity per day
- 51 batches
- Bottleneck
- Heparin-Affinity Elution
Reading the bottleneck
The bottleneck is "Heparin-Affinity Elution": it can process 51 batches per day against a demand of 75 batches, so it falls short of demand by 31.4%. Once downtime and scrap are counted, its cycle time grows from 778 s to 980 s, against a takt of 720 s. The largest loss at this step is equipment downtime (uptime 84%), about 148 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Biologics, mRNA & Cell Therapy: Biologics, mRNA & Cell Therapy
- 2000L Monoclonal Antibody (mAb) CHO Plant
- AAV / Lentiviral Gene Therapy GMP Cleanroom
- Autologous Patient-Specific CAR-T Therapy Lot
- 10,000L Microbial E.Coli Insulin Fermentation
- Human Plasma Immunoglobulin Cold-Ethanol Prep
- Recombinant Antigen + Liposome Vaccine Bulk
- GMP Linearized Plasmid DNA Template Plant
- ISO-7 Single-Use Bioprocess Tubing Assembly
- Antibody-Drug Conjugate (ADC) Payload Link
- Solid-Phase Oligonucleotide & siRNA Synthesis
- Animal-Origin-Free Dry Powder Cell Media Mill