2000L Monoclonal Antibody (mAb) CHO Plant

Product family: Recombinant IgG Biologics.

Flow: Single-Use & Media Suppliers → N-1 Seed Perfusion Rocking Bag → 2000L Fed-Batch Bioreactor → Protein-A & IEX Chrom → Nanofiltration & UF/DF → Cryo-Freeze & Bioassay Release → Sterile Fill-Finish Suites

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 2000L Monoclonal Antibody (mAb) CHO PlantSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Single-Use & Media Suppliers → N-1 Seed Perfusion Rocking Bag (972 s) → 2000L Fed-Batch Bioreactor (1,161 s) → Protein-A & IEX Chrom (1,458 s) → Nanofiltration & UF/DF (1,053 s) → Cryo-Freeze & Bioassay Release (891 s) → Sterile Fill-Finish Suites.SUPPLIERSingle-Use &Media SuppliersI1.60 d1N-1 SeedPerfusion Rockin…C/T 972 sI1.80 d22000L Fed-BatchBioreactorC/T 1,161 sI2.40 d3Protein-A & IEXChromC/T 1,458 sI1.20 d4Nanofiltration &UF/DFC/T 1,053 sI1.50 d5Cryo-Freeze &Bioassay ReleaseC/T 891 sI1.50 dCUSTOMERSterileFill-Finish…60 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. N-1 Seed Perfusion Rocking Bag972 s30 min95%98.4%6096 (1.60 d)76
2. 2000L Fed-Batch Bioreactor1,161 s40 min91%97.2%90108 (1.80 d)60
3. Protein-A & IEX Chrom1,458 s60 min84%94.5%60144 (2.40 d)42
4. Nanofiltration & UF/DF1,053 s25 min93%98.1%3072 (1.20 d)68
5. Cryo-Freeze & Bioassay Release891 s15 min95%97.8%4890 (1.50 d)83

Key figures

Takt time
1,350 s
Lead time
10.1 d
Value-added time
5,535 s
Process cycle efficiency (PCE)
0.68%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
60 batches
Line capacity per day
42 batches
Bottleneck
Protein-A & IEX Chrom

Reading the bottleneck

The bottleneck is "Protein-A & IEX Chrom": it can process 42 batches per day against a demand of 60 batches, so it falls short of demand by 29.8%. Once downtime and scrap are counted, its cycle time grows from 1,458 s to 1,837 s, against a takt of 1,350 s. The largest loss at this step is equipment downtime (uptime 84%), about 278 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.