Antibody-Drug Conjugate (ADC) Payload Link
Product family: OEB-6 Targeted Cancer ADCs.
Flow: mAb Bulk & Cytotoxic Linker → Isolator OEB-6 Linker Solubilize → Antibody Reduction & Conjugate → Cross-Flow Unreacted Toxin Wash → 0.2um Sterile Bulk Filtration → DAR Drug-to-Antibody HPLC → Sterile Lyo Fill-Finish
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Isolator OEB-6 Linker Solubilize | 3,240 s | 30 min | 95% | 98.4% | 12 | 19 (1.58 d) | 15 |
| 2. Antibody Reduction & Conjugate | 3,870 s | 40 min | 91% | 97.2% | 18 | 22 (1.83 d) | 12 |
| 3. Cross-Flow Unreacted Toxin Wash | 4,860 s | 60 min | 84% | 94.5% | 12 | 29 (2.42 d) | 8 |
| 4. 0.2um Sterile Bulk Filtration | 3,510 s | 25 min | 93% | 98.1% | 6 | 14 (1.17 d) | 13 |
| 5. DAR Drug-to-Antibody HPLC | 2,970 s | 15 min | 95% | 97.8% | 10 | 18 (1.50 d) | 17 |
Key figures
- Takt time
- 4,500 s
- Lead time
- 10.3 d
- Value-added time
- 18,450 s
- Process cycle efficiency (PCE)
- 3.3%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 12 batches
- Line capacity per day
- 8 batches
- Bottleneck
- Cross-Flow Unreacted Toxin Wash
Reading the bottleneck
The bottleneck is "Cross-Flow Unreacted Toxin Wash": it can process 8 batches per day against a demand of 12 batches, so it falls short of demand by 31.4%. Once downtime and scrap are counted, its cycle time grows from 4,860 s to 6,122 s, against a takt of 4,500 s. The largest loss at this step is equipment downtime (uptime 84%), about 926 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Biologics, mRNA & Cell Therapy: Biologics, mRNA & Cell Therapy
- 2000L Monoclonal Antibody (mAb) CHO Plant
- AAV / Lentiviral Gene Therapy GMP Cleanroom
- Autologous Patient-Specific CAR-T Therapy Lot
- 10,000L Microbial E.Coli Insulin Fermentation
- Human Plasma Immunoglobulin Cold-Ethanol Prep
- Recombinant Antigen + Liposome Vaccine Bulk
- GMP Linearized Plasmid DNA Template Plant
- ISO-7 Single-Use Bioprocess Tubing Assembly
- Thermostable Taq Polymerase Enzyme Ferment
- Solid-Phase Oligonucleotide & siRNA Synthesis
- Animal-Origin-Free Dry Powder Cell Media Mill