AAV / Lentiviral Gene Therapy GMP Cleanroom

Product family: Adherent/Suspension Gene Vectors.

Flow: Bioreactor and filtration suppliers → Fixed-Bed Plasmid Transfect → Lysis & Nuclease Digestion → Anion-Exchange Empty/Full Cap → Sterile 0.2um Grade-A Bag → ddPCR Titre & Cryo Release → Rare Disease Clinical/Comm

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: AAV / Lentiviral Gene Therapy GMP CleanroomSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Bioreactor and filtration suppliers → Fixed-Bed Plasmid Transfect (2,160 s) → Lysis & Nuclease Digestion (2,580 s) → Anion-Exchange Empty/Full Cap (3,240 s) → Sterile 0.2um Grade-A Bag (2,340 s) → ddPCR Titre & Cryo Release (1,980 s) → Rare Disease Clinical/Comm.SUPPLIERBioreactor andfiltrationsuppliersI1.61 d1Fixed-Bed PlasmidTransfectC/T 2,160 sI1.78 d2Lysis & NucleaseDigestionC/T 2,580 sI2.39 d3Anion-ExchangeEmpty/Full CapC/T 3,240 sI1.22 d4Sterile 0.2umGrade-A BagC/T 2,340 sI1.50 d5ddPCR Titre &Cryo ReleaseC/T 1,980 sI1.50 dCUSTOMERRare DiseaseClinical/Comm18 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Fixed-Bed Plasmid Transfect2,160 s30 min95%98.4%1829 (1.61 d)23
2. Lysis & Nuclease Digestion2,580 s40 min91%97.2%2732 (1.78 d)18
3. Anion-Exchange Empty/Full Cap3,240 s60 min84%94.5%1843 (2.39 d)12
4. Sterile 0.2um Grade-A Bag2,340 s25 min93%98.1%922 (1.22 d)20
5. ddPCR Titre & Cryo Release1,980 s15 min95%97.8%1427 (1.50 d)25

Key figures

Takt time
3,000 s
Lead time
10.2 d
Value-added time
12,300 s
Process cycle efficiency (PCE)
2.2%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
18 batches
Line capacity per day
12 batches
Bottleneck
Anion-Exchange Empty/Full Cap

Reading the bottleneck

The bottleneck is "Anion-Exchange Empty/Full Cap": it can process 12 batches per day against a demand of 18 batches, so it falls short of demand by 31.4%. Once downtime and scrap are counted, its cycle time grows from 3,240 s to 4,082 s, against a takt of 3,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 617 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.