Baffle-Filled 800-Fill RDS Down Puffer Parka

Product family: Zero-Stitch Heat-Sealed Down.

Flow: RDS Certified Goose Down → Ultrasonic Woven Tube Baffle → Laser Cut Ripstop Panels → Gravimetric Down Blower Fill → DWR Seam Tape Waterproof → Feather-Leak Shake & Pack → Outdoor Alpine Brands

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Baffle-Filled 800-Fill RDS Down Puffer ParkaSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. RDS Certified Goose Down → Ultrasonic Woven Tube Baffle (44.0 s) → Laser Cut Ripstop Panels (50.0 s) → Gravimetric Down Blower Fill (74.0 s) → DWR Seam Tape Waterproof (54.0 s) → Feather-Leak Shake & Pack (40.0 s) → Outdoor Alpine Brands.SUPPLIERRDS CertifiedGoose DownI1.60 d1Ultrasonic WovenTube BaffleC/T 44.0 sI1.40 d2Laser Cut RipstopPanelsC/T 50.0 sI2.40 d3Gravimetric DownBlower FillC/T 74.0 sI1.30 d4DWR Seam TapeWaterproofC/T 54.0 sI0.90 d5Feather-LeakShake & PackC/T 40.0 sI1.40 dCUSTOMEROutdoor AlpineBrands780 / garments

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Ultrasonic Woven Tube Baffle44.0 s30 min95%98.8%1,1701,248 (1.60 d)1,126
2. Laser Cut Ripstop Panels50.0 s20 min94%98.2%6241,092 (1.40 d)969
3. Gravimetric Down Blower Fill74.0 s45 min86%93.0%7801,872 (2.40 d)554
4. DWR Seam Tape Waterproof54.0 s15 min92%97.5%4681,014 (1.30 d)872
5. Feather-Leak Shake & Pack40.0 s10 min96%98.5%312702 (0.90 d)1,241

Key figures

Takt time
69.2 s
Lead time
9.00 d
Value-added time
262 s
Process cycle efficiency (PCE)
0.054%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
780 garments
Line capacity per day
554 garments
Bottleneck
Gravimetric Down Blower Fill

Reading the bottleneck

The bottleneck is "Gravimetric Down Blower Fill": it can process 554 garments per day against a demand of 780 garments, so it falls short of demand by 28.9%. Once downtime and scrap are counted, its cycle time grows from 74.0 s to 92.5 s, against a takt of 69.2 s. The largest loss at this step is equipment downtime (uptime 86%), about 12.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Apparel Cut-Make-Trim & Footwear: Apparel Cut-Make-Trim & Footwear