Structured Full-Grain Calfskin Handbag Atelier

Product family: Artisan Edge-Painted Totes.

Flow: Tuscany Full-Grain Tanneries → Vision Hide Defect Die-Cut → Skiving & Structural Reinforce → Saddle Stitch & 4-Coat Edge → 24k Brass Clasp Riveting → UV Micro-Inspection & Dustbag → Flagship Luxury Boutiques

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Structured Full-Grain Calfskin Handbag AtelierSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Tuscany Full-Grain Tanneries → Vision Hide Defect Die-Cut (123 s) → Skiving & Structural Reinforce (139 s) → Saddle Stitch & 4-Coat Edge (206 s) → 24k Brass Clasp Riveting (150 s) → UV Micro-Inspection & Dustbag (112 s) → Flagship Luxury Boutiques.SUPPLIERTuscanyFull-GrainTanneriesI1.60 d1Vision HideDefect Die-CutC/T 123 sI1.40 d2Skiving &Structural…C/T 139 sI2.40 d3Saddle Stitch &4-Coat EdgeC/T 206 sI1.30 d424k Brass ClaspRivetingC/T 150 sI0.90 d5UVMicro-Inspection…C/T 112 sI1.40 dCUSTOMERFlagship LuxuryBoutiques140 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Vision Hide Defect Die-Cut123 s30 min95%98.8%210224 (1.60 d)197
2. Skiving & Structural Reinforce139 s20 min94%98.2%112196 (1.40 d)169
3. Saddle Stitch & 4-Coat Edge206 s45 min86%93.0%140336 (2.40 d)94
4. 24k Brass Clasp Riveting150 s15 min92%97.5%84182 (1.30 d)152
5. UV Micro-Inspection & Dustbag112 s10 min96%98.5%56126 (0.90 d)215

Key figures

Takt time
193 s
Lead time
9.03 d
Value-added time
730 s
Process cycle efficiency (PCE)
0.30%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
140 units
Line capacity per day
94 units
Bottleneck
Saddle Stitch & 4-Coat Edge

Reading the bottleneck

The bottleneck is "Saddle Stitch & 4-Coat Edge": it can process 94 units per day against a demand of 140 units, so it falls short of demand by 32.6%. Once downtime and scrap are counted, its cycle time grows from 206 s to 258 s, against a takt of 193 s. The largest loss at this step is equipment downtime (uptime 86%), about 33.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.