S3 Composite-Toe PU Direct-Injection Work Boot
Product family: Steel-Free Safety Footwear.
Flow: Waterproof Nubuck & Aramid → Steel Die Leather Clicking → Automatic Upper Stitching → Lasting & Dual-Density PU Mold → Trim Flash & Steel-Free Stamp → EN-ISO 20345 Drop Audit → Industrial PPE Wholesalers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Steel Die Leather Clicking | 24.7 s | 30 min | 95% | 98.8% | 2,100 | 2,240 (1.60 d) | 2,006 |
| 2. Automatic Upper Stitching | 27.8 s | 20 min | 94% | 98.2% | 1,120 | 1,960 (1.40 d) | 1,743 |
| 3. Lasting & Dual-Density PU Mold | 41.0 s | 45 min | 86% | 93.0% | 1,400 | 3,360 (2.40 d) | 1,001 |
| 4. Trim Flash & Steel-Free Stamp | 30.1 s | 15 min | 92% | 97.5% | 840 | 1,820 (1.30 d) | 1,565 |
| 5. EN-ISO 20345 Drop Audit | 22.4 s | 10 min | 96% | 98.5% | 560 | 1,260 (0.90 d) | 2,216 |
Key figures
- Takt time
- 38.6 s
- Lead time
- 9.00 d
- Value-added time
- 146 s
- Process cycle efficiency (PCE)
- 0.030%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 1,400 units
- Line capacity per day
- 1,001 units
- Bottleneck
- Lasting & Dual-Density PU Mold
Reading the bottleneck
The bottleneck is "Lasting & Dual-Density PU Mold": it can process 1,001 units per day against a demand of 1,400 units, so it falls short of demand by 28.5%. Once downtime and scrap are counted, its cycle time grows from 41.0 s to 51.3 s, against a takt of 38.6 s. The largest loss at this step is equipment downtime (uptime 86%), about 6.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Apparel Cut-Make-Trim & Footwear: Apparel Cut-Make-Trim & Footwear
- Apparel Cut-Make-Trim (CMT) Garment Line
- Ozone & Laser Distressed Denim Jeans Line
- Seamless Circular Activewear Line
- Bespoke Tailored Men’s Merino Wool Suit Line
- EN-11612 Arc-Flash Flame-Retardant Coverall
- Direct-Injected PU/TPU Knit Running Shoe Line
- Structured Full-Grain Calfskin Handbag Atelier
- Class-II Medical Graduated Compression Stocking
- Chlorine-Proof Recycled Nylon Bikini & Swim Trunks
- Baffle-Filled 800-Fill RDS Down Puffer Parka
- Custom Sports Club Dye-Sublimation Jersey Line