Ozone & Laser Distressed Denim Jeans Line
Product family: Sustainable Stretch Jeans.
Flow: Premium denim mills → CAD Marker Nest & Cut → Twin-Needle Chainstitch Line → 3D Laser Whisker & Ozone Wash → Rivet Press & Steam Form → AQL 2.5 Shade & Tag Pack → Global Denim Retailers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. CAD Marker Nest & Cut | 14.4 s | 30 min | 95% | 98.8% | 3,600 | 3,840 (1.60 d) | 3,442 |
| 2. Twin-Needle Chainstitch Line | 16.2 s | 20 min | 94% | 98.2% | 1,920 | 3,360 (1.40 d) | 2,991 |
| 3. 3D Laser Whisker & Ozone Wash | 24.1 s | 45 min | 86% | 93.0% | 2,400 | 5,760 (2.40 d) | 1,702 |
| 4. Rivet Press & Steam Form | 17.6 s | 15 min | 92% | 97.5% | 1,440 | 3,120 (1.30 d) | 2,676 |
| 5. AQL 2.5 Shade & Tag Pack | 13.0 s | 10 min | 96% | 98.5% | 960 | 2,160 (0.90 d) | 3,819 |
Key figures
- Takt time
- 22.5 s
- Lead time
- 9.00 d
- Value-added time
- 85.3 s
- Process cycle efficiency (PCE)
- 0.018%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 2,400 garments
- Line capacity per day
- 1,702 garments
- Bottleneck
- 3D Laser Whisker & Ozone Wash
Reading the bottleneck
The bottleneck is "3D Laser Whisker & Ozone Wash": it can process 1,702 garments per day against a demand of 2,400 garments, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 24.1 s to 30.1 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 86%), about 3.9 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Apparel Cut-Make-Trim & Footwear: Apparel Cut-Make-Trim & Footwear
- Apparel Cut-Make-Trim (CMT) Garment Line
- Seamless Circular Activewear Line
- Bespoke Tailored Men’s Merino Wool Suit Line
- EN-11612 Arc-Flash Flame-Retardant Coverall
- Direct-Injected PU/TPU Knit Running Shoe Line
- Structured Full-Grain Calfskin Handbag Atelier
- S3 Composite-Toe PU Direct-Injection Work Boot
- Class-II Medical Graduated Compression Stocking
- Chlorine-Proof Recycled Nylon Bikini & Swim Trunks
- Baffle-Filled 800-Fill RDS Down Puffer Parka
- Custom Sports Club Dye-Sublimation Jersey Line