Class-8 Long-Haul Sleeper Cab Body & Trim

Product family: Aerodynamic Steel/SMC Sleeper Cabs.

Flow: Truck stamping supplier → Underbody & Firewall Jig → Sleeper Roof Laser Seam → Primer Electro-Coat Dip → Glass, Bunk & Dash Trim → Monsoon Spray & Cab Tilt QC → Heavy Truck Chassis Drop

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Class-8 Long-Haul Sleeper Cab Body & TrimSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Truck stamping supplier → Underbody & Firewall Jig (445 s) → Sleeper Roof Laser Seam (540 s) → Primer Electro-Coat Dip (680 s) → Glass, Bunk & Dash Trim (508 s) → Monsoon Spray & Cab Tilt QC (368 s) → Heavy Truck Chassis Drop.SUPPLIERTruck stampingsupplierI2.00 d1Underbody &Firewall JigC/T 445 sI2.20 d2Sleeper RoofLaser SeamC/T 540 sI2.40 d3PrimerElectro-Coat DipC/T 680 sI1.51 d4Glass, Bunk &Dash TrimC/T 508 sI0.91 d5Monsoon Spray &Cab Tilt QCC/T 368 sI2.00 dCUSTOMERHeavy TruckChassis Drop85 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Underbody & Firewall Jig445 s35 min94%98.8%85170 (2.00 d)108
2. Sleeper Roof Laser Seam540 s50 min89%96.5%85187 (2.20 d)81
3. Primer Electro-Coat Dip680 s40 min84%95.2%43204 (2.40 d)58
4. Glass, Bunk & Dash Trim508 s30 min91%97.1%85128 (1.51 d)91
5. Monsoon Spray & Cab Tilt QC368 s10 min96%98.9%2177 (0.91 d)133

Key figures

Takt time
635 s
Lead time
11.1 d
Value-added time
2,541 s
Process cycle efficiency (PCE)
0.43%
Rolled throughput yield (RTY)
87.2%
Customer demand per day
85 units
Line capacity per day
58 units
Bottleneck
Primer Electro-Coat Dip

Reading the bottleneck

The bottleneck is "Primer Electro-Coat Dip": it can process 58 units per day against a demand of 85 units, so it falls short of demand by 31.9%. Once downtime and scrap are counted, its cycle time grows from 680 s to 850 s, against a takt of 635 s. The largest loss at this step is equipment downtime (uptime 84%), about 130 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.