Municipal Aerial Ladder Fire Apparatus Body
Product family: Aluminum Pumping Rescue Bodies.
Flow: Pump & aluminum extrusion supplier → Extruded Locker Frame → 3000L Poly Water Tank Drop → Centrifugal Pump Plumb → CAN-Bus Scene Light & Ladder → NFPA Pump & Tilt Cert → City Fire Departments
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Extruded Locker Frame | 3,150 s | 35 min | 94% | 98.8% | 6 | 12 (2.00 d) | 7 |
| 2. 3000L Poly Water Tank Drop | 3,825 s | 50 min | 89% | 96.5% | 6 | 13 (2.17 d) | 5 |
| 3. Centrifugal Pump Plumb | 4,815 s | 40 min | 84% | 95.2% | 3 | 14 (2.33 d) | 4 |
| 4. CAN-Bus Scene Light & Ladder | 3,600 s | 30 min | 91% | 97.1% | 6 | 9 (1.50 d) | 6 |
| 5. NFPA Pump & Tilt Cert | 2,610 s | 10 min | 96% | 98.9% | 2 | 5 (0.83 d) | 9 |
Key figures
- Takt time
- 4,500 s
- Lead time
- 11.5 d
- Value-added time
- 18,000 s
- Process cycle efficiency (PCE)
- 5.8%
- Rolled throughput yield (RTY)
- 87.2%
- Customer demand per day
- 6 units
- Line capacity per day
- 4 units
- Bottleneck
- Centrifugal Pump Plumb
Reading the bottleneck
The bottleneck is "Centrifugal Pump Plumb": it can process 4 units per day against a demand of 6 units, so it falls short of demand by 38.6%. Once downtime and scrap are counted, its cycle time grows from 4,815 s to 6,021 s, against a takt of 4,500 s. The largest loss at this step is equipment downtime (uptime 84%), about 917 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Commercial Trucks, Bus & Rail: Commercial Trucks, Bus & Rail
- Class-8 Long-Haul Sleeper Cab Body & Trim
- 12m Low-Floor Electric Transit Bus Build
- High-Speed Passenger Rail Bogie Assembly
- Plug-Sliding Pneumatic Metro Car Door
- Heavy Truck EBS Electronic Brake Valve
- 40ft Curtain-Sider Semi-Trailer Frame
- CVT Continuous Agricultural Tractor Gearbox
- 3-Stage Triplex Tele-Mast Warehouse Forklift
- 24-Ton Excavator Articulated Boom & Stick
- 2500-Bar Heavy Diesel Common-Rail Pump
- 5-Piece Off-The-Road Mining Haul Truck Rim