24-Ton Excavator Articulated Boom & Stick

Product family: Heavy High-Strength Fabricated Booms.

Flow: Wear-plate steel supplier → Bevel Plasma Thick Plate → Dual-Robot Tandem Boom Weld → UT Critical Joint Inspection → Portable Line-Bore Pin Eyes → Primer Blast & Gloss Yellow → Earthmoving OEM Final Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 24-Ton Excavator Articulated Boom & StickSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Wear-plate steel supplier → Bevel Plasma Thick Plate (1,181 s) → Dual-Robot Tandem Boom Weld (1,434 s) → UT Critical Joint Inspection (1,806 s) → Portable Line-Bore Pin Eyes (1,350 s) → Primer Blast & Gloss Yellow (979 s) → Earthmoving OEM Final Line.SUPPLIERWear-platesteel supplierI2.00 d1Bevel PlasmaThick PlateC/T 1,181 sI2.19 d2Dual-Robot TandemBoom WeldC/T 1,434 sI2.41 d3UT Critical JointInspectionC/T 1,806 sI1.50 d4PortableLine-Bore Pin…C/T 1,350 sI0.91 d5Primer Blast &Gloss YellowC/T 979 sI2.00 dCUSTOMEREarthmoving OEMFinal Line32 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Bevel Plasma Thick Plate1,181 s35 min94%98.8%3264 (2.00 d)41
2. Dual-Robot Tandem Boom Weld1,434 s50 min89%96.5%3270 (2.19 d)31
3. UT Critical Joint Inspection1,806 s40 min84%95.2%1677 (2.41 d)22
4. Portable Line-Bore Pin Eyes1,350 s30 min91%97.1%3248 (1.50 d)34
5. Primer Blast & Gloss Yellow979 s10 min96%98.9%829 (0.91 d)50

Key figures

Takt time
1,688 s
Lead time
11.1 d
Value-added time
6,750 s
Process cycle efficiency (PCE)
1.1%
Rolled throughput yield (RTY)
87.2%
Customer demand per day
32 parts
Line capacity per day
22 parts
Bottleneck
UT Critical Joint Inspection

Reading the bottleneck

The bottleneck is "UT Critical Joint Inspection": it can process 22 parts per day against a demand of 32 parts, so it falls short of demand by 31.9%. Once downtime and scrap are counted, its cycle time grows from 1,806 s to 2,258 s, against a takt of 1,688 s. The largest loss at this step is equipment downtime (uptime 84%), about 344 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Commercial Trucks, Bus & Rail: Commercial Trucks, Bus & Rail