5-Piece Off-The-Road Mining Haul Truck Rim

Product family: 63-Inch Ultra-Class Earthmover Rims.

Flow: Heavy plate steel supplier → Roll-Bend Barrel & Weld → Lock-Ring Gutter Roll Press → Mag-Particle Crack Inspect → Disc-to-Rim Submerged Arc → High-Build Zinc Epoxy Coat → Open-Pit Mining Fleets

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 5-Piece Off-The-Road Mining Haul Truck RimSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Heavy plate steel supplier → Roll-Bend Barrel & Weld (1,350 s) → Lock-Ring Gutter Roll Press (1,639 s) → Mag-Particle Crack Inspect (2,064 s) → Disc-to-Rim Submerged Arc (1,543 s) → High-Build Zinc Epoxy Coat (1,119 s) → Open-Pit Mining Fleets.SUPPLIERHeavy platesteel supplierI2.00 d1Roll-Bend Barrel& WeldC/T 1,350 sI2.21 d2Lock-Ring GutterRoll PressC/T 1,639 sI2.39 d3Mag-ParticleCrack InspectC/T 2,064 sI1.50 d4Disc-to-RimSubmerged ArcC/T 1,543 sI0.89 d5High-Build ZincEpoxy CoatC/T 1,119 sI2.00 dCUSTOMEROpen-Pit MiningFleets28 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Roll-Bend Barrel & Weld1,350 s35 min94%98.8%2856 (2.00 d)36
2. Lock-Ring Gutter Roll Press1,639 s50 min89%96.5%2862 (2.21 d)27
3. Mag-Particle Crack Inspect2,064 s40 min84%95.2%1467 (2.39 d)19
4. Disc-to-Rim Submerged Arc1,543 s30 min91%97.1%2842 (1.50 d)30
5. High-Build Zinc Epoxy Coat1,119 s10 min96%98.9%725 (0.89 d)44

Key figures

Takt time
1,929 s
Lead time
11.1 d
Value-added time
7,715 s
Process cycle efficiency (PCE)
1.3%
Rolled throughput yield (RTY)
87.2%
Customer demand per day
28 parts
Line capacity per day
19 parts
Bottleneck
Mag-Particle Crack Inspect

Reading the bottleneck

The bottleneck is "Mag-Particle Crack Inspect": it can process 19 parts per day against a demand of 28 parts, so it falls short of demand by 31.9%. Once downtime and scrap are counted, its cycle time grows from 2,064 s to 2,581 s, against a takt of 1,929 s. The largest loss at this step is equipment downtime (uptime 84%), about 393 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.